Buckreef Gold Mine Declares Commercial Production of 1,000 Tonnes Per Day

new CIL tanks at Buckreef

On 15th November 2022, TRX Gold Corporation (TSX:TNX) (NYSE American:TRX) reported its declaration of commercial production of the 1,000+ tonnes per day (tpd) processing plant at the Buckreef Gold Mine in north-central Tanzania.

The declaration of commercial production was made after successful construction, commissioning, and ramp-up of processing to a steady state throughput of 1,000+ tpd.

TRX explains that the processing plant has been running consistently at or above nameplate capacity since October 2022 with gold recoveries exceeding budget with 2,200 ounces of gold poured during the month (22% above plan).

TANZANIA BUSINESS & INVESTMENT GUIDE 2026

Stephen Mullowney, CEO of TRX commented: “The Board, Executive Management and I are very excited to have reached this remarkable milestone in the Company’s history. During the last 12 months, the Buckreef Gold team has delivered excellence in safety and built not only a great 1,000+ tpd processing plant but also a track record for achievement. While we celebrate this goal, we are also ready to advance the growth of the business with improvement initiatives, exploration, and ever-increasing production. TRX Gold and Buckreef Gold are currently evaluating a potential further near-term expansion of the processing plant.”

Tanzania Gold

Tanzania is the 4th largest gold producer in Africa after South Africa, Ghana, and Mali and accounts for 1.3% of the total global gold production.

Tanzania’s gold reserves are estimated at about 45 million ounces and Tanzania’s gold production in Tanzania stands at around 50t per year.

Want to know more about Mining in Tanzania? Our free Tanzania Business and Investment Guide 2026 covers Mining, plus regulations, key sectors, and investment opportunities — all in one place.

Download Free Guide
Related Posts
Tanzania Mahenge Graphite Project Map
Read More

Tanzania Mahenge Graphite Project Early Works to Complete by Mid-2026 Ahead of Final Investment Decision

Black Rock Mining's early works program at the Mahenge Graphite Project in Tanzania's Ulanga region is nearing completion, with final earthworks and resettlement activities expected to wrap up by late Q2 2026. Community compensation for the lower access road has been completed, the 220kV transmission line survey is finished, and all early works pricing has been validated against the 2022 FEED, positioning the project for a rapid construction ramp-up once full funding and a Final Investment Decision are secured.
Tanzania Panda Hill Niobium Agreement Signing
Read More

Tanzania Signs Niobium Project Agreement Targeting 4% of Global Output

The Government of Tanzania and Panda Hill Tanzania Limited have officially signed an agreement to advance the Panda Hill niobium project in Mbeya. The deal formalizes government participation through a 16% free carried interest, positions Tanzania to contribute 4% of global niobium supply, and includes the construction of a ferroniobium plant, local value addition, and thousands of jobs over the project’s life.