Availability of Tanzania Electric Services to Improve

Tanzania Electric Supply Company (TANESCO) has released plans to invest USD 33.4 million in order to add a 134–kilometer high-voltage power transmission line to its current network, thus making it possible for the company to serve as many as 25,000 new customers.

In order for this plan to be realized, TANESCO has joined forces in a signed agreement with SAE Power Lines (Milan, Italy) and Associated Transrail Structures Limited (Milan), who will be responsible for the implementation of the project.

This new 132-kilovolt (kV) transmission network reinforcement project is one piece of the Tanzania Energy Development and Access Expansion Project (TEPAD).

Other pieces of the project include plans to construct 13 new distribution stations and to re-establish five existing substations as well as to begin improving the company’s current network, in part by replacing 60,000 credit meters with prepaid ones.

Tanzania Investment Guide 2026 Free Edition

In addition, TANESCO plans to install solid-state meters with remote metering for 1,800 customers and to establish a technical service management system, a resource management system, a commercial management system, and a marketing department.

Currently, low network voltages combined with high energy losses in most regions has resulted in limited customer access to power, therefore, one of the aims of the project is to provide new households and businesses with more frequent access to the national power grid system.

Until now, Tanzania has not yet begun to generate surplus power, meaning that, should there be a breakdown in the power supply, the only available option is for the government to ration the power supply.

The current peak power demand of Tanzania stands at approximately 787 megawatts (MW) and a grid that is capable of supplying only 595 MW and it has been predicted that the power demand for the country will increase to 1,331 MW along with an increased overall capacity of 1,445 MW by 2014.

In order to meet the increasing demand of the country, TANESCO has calculated that the country would need to add at least 105 MW of power to its grid annually.

Tanzania Investment Guide 2026 Full Edition

To this end, one of the primary goals in the formation and development of the TEPAD project is to improve the overall power services that are available in the country’s three major growth centers, including in and around the capital city of Dar es Salaam, the Mount Kilimanjaro and Arusha.

Included in the plans of the project is the investment in TANESCO’s current transmission and distribution network along with the extension of support to the Rural Energy Agency, and the guaranteed supply of the finances that are required both for project management and for technical assistance.

Estimate for the overall cost of the project, made by the World Bank in Washington, D.C., have priced the project at approximately USD 105 million.

Want to know more about Mining in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Mining, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Related Posts
Tanzania gold production 2025-2026
Read More

Tanzania Gold Production Reaches 67.8 Tonnes, Central Bank Buys 75.64%

Tanzania's Ministry of Minerals reported that the country produced 67.8 tonnes of gold worth TZS 18.4 trillion in the 2025/26 financial year, with 28,701 kilograms sold through five domestic refineries. The Bank of Tanzania purchased 21,710 kilograms, equivalent to 75.64% of that volume, under its Domestic Gold Purchase Programme to strengthen the country's foreign reserves.
North Rukwa Project helium licence map, Tanzania
Read More

Noble Helium Raises AUD 12 Million, Secures Rig for North Rukwa Drilling

Noble Helium Limited (ASX:NHE) raised AUD 12 million and converted AUD 6.603 million of debt to equity during the June 2026 quarter, ending with AUD 6.689 million in cash, according to its latest quarterly report. The company has contracted a rig to drill two wells at its Kinambo prospect within the North Rukwa Project in Tanzania, with mobilisation expected in August 2026.
Tanzania Mineral Testing Laboratory Dodoma 3d plan
Read More

Dodoma Mineral Testing Laboratory on Track for September 2027 Completion

The Geological Survey of Tanzania (GST) says construction of its Dodoma mineral testing laboratory in Kizota, Dodoma, is progressing on schedule, with completion set for September 2027, a year after Minister for Minerals Anthony Mavunde laid the foundation stone in August 2025. The TZS 14.3 billion (approx. USD 5.4 million) facility is expected to become the largest of its kind in East and Central Africa, offering internationally accredited testing services and easing long-standing sample-analysis delays for artisanal and small-scale miners.
IMF Tanzania flag
Read More

IMF Approves USD 443.9 Million for Tanzania, Projects 6.2% GDP Growth Supported by Mining, Agriculture, and Tourism

The IMF Executive Board has approved an immediate disbursement of USD 443.9 million to Tanzania after completing the final reviews under the Extended Credit Facility and Resilience and Sustainability Facility programmes. The IMF said Tanzania maintained strong economic growth and macroeconomic stability while highlighting the need for continued reforms and fiscal consolidation.