Tanzania Airports Authority Licenses BAM International To Start Phase 2 Of Dar Es Salaam Julius Neyerere International Airport New Terminal 3

Julius Nyerere International Airport new terminal 3

Dutch contractor BAM International (BAM) has recently received the license from Tanzania Airports Authority (TAA) to start construction works of Phase 2 of the new Terminal 3 at the Julius Nyerere International Airport.

The project for a total investment of EUR 100 million was awarded in 2013 by TAA and partially financed by the Tanzanian Government and the ORET Fund from the Dutch Ministry of Foreign Affairs, will be executed in a joint venture with the UK based BAM Nuttall and the Dutch BAM Advies & Engineering as the designers.

According to BAM, the new terminal is meant to meet the future growth on international arrivals by extending capacity to 6 million passengers per annum in a total terminal area of 60,000 square metres.

Tanzania Investment Guide 2026 Free Edition

In 2014 the total flow of passengers to Julius Nyerere International Airport reached 2.5 million.

Terminals 1 and 2 will be used for domestic flights , which have grown 7.4% in 2014.

Upgrades on the ground lighting system, existing taxiways, secondary runway and apron, and improvements at the drainage system and environmental situation in the areas surrounding the airport are also included in Phase 2.

It follows the rehabilitation of DAR airport Phase 1 which aimed at returning the 3.1 km runway and apron at the terminal 2 to international aviation standards set by the International Civil Aviation Organization (ICAO), and that was completed between 2005 and 2006 at a total cost of EUR 130 million.

With the completion of both phases, TAA expects to handle at DAR airport an extended capacity over the 30 planes per hour up from the current 11 and 8.9 planes per hour recorded in 2014.

TanzaniaInvest Capital Markets Report Banner

Want to know more about Transport in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Transport, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Related Posts
Samia Suluhu Hassan Ndiame Diop World Bank Dar es Salaam Port Second Phase
Read More

World Bank Considers Financing Second Phase of Dar es Salaam Port Upgrade

The World Bank is considering financing a second phase of the Dar es Salaam Port upgrade after the first phase, backed by a USD 345 million credit, reached 85% completion and helped raise annual throughput from 14 million tonnes in 2015/16 to 32.8 million tonnes in 2025/26. Regional Vice President Ndiamé Diop signalled the interest during a three-day visit that included talks with President Samia Suluhu Hassan on 20 August 2026 covering the SGR, central corridor development, agriculture, education and the mobilisation of private investment.
Tanzania Samia Suluhu Hassan DRC Felix Tshisekedi
Read More

DRC to Build Dry Port in Dar es Salaam, Deepen Transport and Mining Ties with Tanzania

The Democratic Republic of the Congo (DRC) has begun preparations to build a dry port in Dar es Salaam that will provide customs, cargo handling, mineral certification, and quality control services for Congolese goods moving through Tanzania, President Félix Tshisekedi announced during a state visit to Tanzania on 18 August 2026. The DRC is among the largest users of Tanzanian ports, with approximately 7.2 million tonnes of cargo handled in 2023, as the two countries agreed to accelerate transport, trade, and mining cooperation along the Central Corridor.
Tanzania President Samia Suluhu Hassan foundation stone construction Tabora-Kigoma Standard Gauge Railway (SGR)
Read More

Tanzania Begins Construction of USD 2.74 Billion Tabora-Kigoma SGR Railway Section

President Samia Suluhu Hassan laid the foundation stone for the 506-kilometer Tabora-Kigoma Standard Gauge Railway (SGR) section on 20 July 2026, a USD 2.74 billion (TZS 7.4 trillion) investment linking Dar es Salaam Port to Lake Tanganyika. The section forms the second phase of Tanzania's SGR program, alongside the planned Uvinza-Musongati line, and is expected to position Kigoma as a regional trade hub connecting Tanzania to Burundi, the Democratic Republic of Congo and Zambia.