Iringa-Shinyanga Electricity Project to be Completed in September 2016

The Iringa-Shinyanga Backbone Transmission Investment Project (BTIP) is expected to be completed in September 2016, according to a recent speech by the Tanzanian Minister of Energy and Minerals, Sospeter Muhongo.

The project is funded by various sources including the African Development Bank (AfDB) and the Japan International Cooperation Agency (JICA). The executing agency is the Tanzania Electric Supply Company (TANESCO).

The Iringa-Shinyanga power line intends to reinforce the existing 220kV transmission line from Iringa to Shinyanga by constructing approximately 700km of 400kV electrical power transmission line and associated facilities.

Tanzania Investment Guide 2026 Free Edition

The Iringa-Shinyanga transmission line is divided into 3 line sections: Iringa-Dodoma (225km), Dodoma-Singida (227km), and Singida-Shinyanga (228km).

According to AfDB, strengthening of the grid is a key component of regional economic cooperation and development for future interconnections with neighboring countries.

According to JICA, the extension of substations connecting the lines will increase the quantity and reliability of power supplied from the southern regions of Tanzania to the northern regions, where the demand for power is rising.

It will also improve living standards and will stimulate economic activities including mining development.

The Chief Energy Engineer of the Tanzanian Ministry of Energy and Minerals, Mr Salum Inegeja, told local media that the completion of the project will enable Tanzania to participate actively in electricity commerce through the grid systems in the Eastern region (Eastern African Power Pool, EAPP) and the Southern region (Southern African Power Pool, SAPP).

TanzaniaInvest Capital Markets Report Banner

He also added that this project is part of a larger electricity project connecting Zambia, Tanzania and Kenya.

The 2,300km Zambia-Tanzania-Kenya Interconnection Project intends to connect the Zambian grid to Kenya, via Tanzania, to facilitate power trade, reduce average energy production costs and improve reliability and security of power supply to both Southern and Eastern Africa.

For this, the governments of Zambia, Tanzania and Kenya signed a Memorandum of Understanding (MoU) in 2014 to fund the project.

Expected results include facilitation of the wheeling of 400MW of electric power from Zambia to Tanzania and facilitation of wheeling at least 300MW from Tanzania to Kenya.

The ZTK line is expected to be operational in 2018, according to the New Partnership for Africa’s Development (NEPAD).

Want to know more about Energy in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Energy, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Related Posts
Read More

EU–Tanzania Roadshow Continues in Italy With Rice, Cashew, Coffee and Renewable Energy Investment Pitches in Cesena

At the Cesena stop of the EU–Tanzania roadshow, Tanzanian agencies presented investment opportunities in rice, cashew and coffee processing, renewable energy, power transmission and digital infrastructure. Italy’s Ministry of Foreign Affairs cited USD 8.6 billion in foreign investment registered in Tanzania in the last year, up 56%, while EU and Italian institutions outlined grants, guarantees, export credit and blended finance.
Songo Songo Offshore Gas
Read More

Orca Warns Its Operation of Tanzania’s Songo Songo Gas Field May End on 10 October as Sale Awaits Approvals

Orca Energy Group has warned that its subsidiary may cease operating Tanzania’s Songo Songo gas field, which supplies natural gas to power plants and industries, when its licence expires on 10 October 2026. The proposed sale to Taifa Gas and Amber Energy Investment remains subject to approvals, and PanAfrican Energy Tanzania has recommended preparations for a possible transfer of operating responsibilities.
Tanzania Julius Nyerere Hydropower Project (JNHPP)
Read More

Tanzania Electricity Surplus Hits 2,375 MW As Julius Nyerere Hydropower Project Is Officially Launched

The Julius Nyerere Hydropower Project's 2,115MW plant lifted Tanzania's installed generation capacity to 4,646MW against peak demand of 2,271MW, with a surplus of 2,375MW, after President Samia Suluhu Hassan's inauguration on 22 August 2026. The government has signed an agreement to export power to Zambia and reached a trading arrangement with Kenya, while a newly completed 400kV Chalinze-Dodoma transmission line lifted national peak demand by 150MW within three days of coming online.
Presidents Samia Suluhu Hassan and Yoweri Museveni witness the Tanga Regional Energy Hub MoU signing, State House Dar es Salaam
Read More

Tanzania, Uganda Sign MoU for USD 20 Billion Tanga Energy Hub

Tanzania and Uganda signed a Memorandum of Understanding at State House on 6 August 2026 to develop Tanga as a Regional Energy Hub, a deal Tanzania's Energy Minister said could attract investment exceeding USD 20 billion. The agreement, signed by the Uganda National Oil Company, the Tanzania Petroleum Development Corporation, and Vitol Bahrain E.C., covers petroleum storage, refining, logistics, and distribution infrastructure at the port of Tanga, building on the East African Crude Oil Pipeline.