Mtwara Port Expansion Works Started

Mtwara Port Map

On March 4, 2017 Tanzanian President John Magufuli placed the foundation stone for the expansion works at the Mtwara port in southern Tanzania.

The construction works for a new 350-meter long berth will take 21 months to be completed.

This will greatly enhance the port’s capacity to accommodate large vessels to dock and to serve Dangote’s 3.0Mta cement plant in Mtwara, as well as increase the port’s overall cargo capacity, the Tanzania Ports Authority (TPA) indicates.

Tanzania Investment Guide 2026 Free Edition

The Mtwara port transported 273,886 metric tons of cargo in 2015/2016 and 388,000 tons in 2016/2017, approaching the port’s maximum cargo capacity of 400,000 tons per year.

The port is one of the three major ports of Tanzania. Others are Dar es Salaam, and Tanga in the north.

The port is destined to be an alternative cargo gateway for cargo bound for southern Tanzania, Malawi, Eastern Zambia and Northern Mozambique.

The Mtwara port has witnessed an increased in activity since the beginning of offshore oil and gas exploration activities in Southern Tanzania.

Furthermore, the Liganga iron ore and the Mchuchuma coal mining projects are also expected to use the Mtwara port.

Tanzania Investment Guide 2026 Full Edition

The port is also an integral part of the Mtwara Development Corridor project and has a special economic zone attached to it.

Want to know more about Transport in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Transport, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources.

Download Free OverviewGet the Full Guide
Related Posts
Tanzania President Samia Suluhu Hassan foundation stone construction Tabora-Kigoma Standard Gauge Railway (SGR)
Read More

Tanzania Begins Construction of USD 2.74 Billion Tabora-Kigoma SGR Railway Section

President Samia Suluhu Hassan laid the foundation stone for the 506-kilometer Tabora-Kigoma Standard Gauge Railway (SGR) section on 20 July 2026, a USD 2.74 billion (TZS 7.4 trillion) investment linking Dar es Salaam Port to Lake Tanganyika. The section forms the second phase of Tanzania's SGR program, alongside the planned Uvinza-Musongati line, and is expected to position Kigoma as a regional trade hub connecting Tanzania to Burundi, the Democratic Republic of Congo and Zambia.
Ministry of Finance pavilion at the 2026 Public Service Week in Dodoma
Read More

Tanzania Signs Nine PPP Contracts for DART, Ports and TAZARA Railway

Tanzania has signed nine public-private partnership (PPP) contracts as of June 2026, as it uses the model to accelerate major strategic projects, improve public services, and attract investment. The contracts cover the Dar es Salaam Rapid Transit (DART) system, mandatory motor vehicle inspection, the Kariakoo commercial building, the TAZARA railway, and the operation of the Dar es Salaam Port through DP World and Adani.