Singida Mine Remains on Track for First Gold Pour in March 2023

SINGIDA GOLD PROJECT CONSTRUCTION

East Africa-focused gold producer, developer, and explorer Shanta Gold (AIM: SHG), recently released its production and operational results for the quarter and year ended 31 December 2022 for its East African assets, including the New Luika Gold Mine and the Singida Project in Tanzania.

In the update, Eric Zurrin, Chief Executive Officer, commented: “We enjoyed a strong end to the year at all of our assets across the portfolio, with several positive signs pointing to what we hope will be an exciting 2023 for the company. An encouraging operational end to the year at New Luika saw record annual throughput and full-year production of 65,209 ounces, an 18% increase vs last year’s production figures.”

The update also indicates that the Singida Project is 90% complete as of the end of December 2022, on budget, and on track for the first production of gold in March 2023.

Hot commissioning of the process plant is planned for March 2023 following the installation of the COMO engineering elution and electrowinning circuit.

Singida Gold Project

The Singida gold mine is located in the Ikungi region of Central Tanzania. Shanta Mining Company Limited holds 100% of the mining licenses. The current Life of Mine extends to the end of 2029, based on existing reserves.

Mining operations commenced in September 2021, with ore currently being stockpiled, until it can be processed through the Carbon in Leach plant, which is currently being constructed.

Tanzania Gold

Tanzania’s gold reserves are estimated at about 45 million ounces and Tanzania’s gold production in Tanzania stands at around 50t per year.

Shanta Gold’s New Luika Gold Mine is currently the 4th largest mine in the country with gold production of about 80,000 ounces per year although it was only 55,280 ounces in 2021.

Want to know more about Mining in Tanzania? Our free Tanzania Business and Investment Guide 2026 covers Mining, plus regulations, key sectors, and investment opportunities — all in one place.

Download Free Guide
Related Posts
Anthony Mavunde Parliament Bunge
Read More

Tanzania’s 2026/27 Mining Budget Sets Ambition for Critical Minerals Leadership and Top-4 Global Niobium Producer Status

Tanzania's Ministry of Minerals has tabled a TZS 174.98 billion budget for FY 2026/27, with a revenue collection target of TZS 1.41 trillion from a sector whose GDP contribution has climbed to 11.9% and whose exports rose 31.1% to USD 5,401.9 million in 2025. The budget prioritises critical and strategic minerals, the Panda Hill niobium project expected to make Tanzania a top-4 global producer, the Buzwagi value-addition hub, and expanding geophysical survey coverage to 50% of the country by 2030.
Tanzania mineral processing
Read More

Tanzania to Build Mineral Processing Center in Shinyanga to Boost Value Addition

The Tanzanian government plans to establish a Mineral Processing Center in Mwakitolyo, Shinyanga Region, to deepen mineral value addition and expand local participation in the mineral value chain. Deputy Minister for Minerals Dr. Steven Kiruswa highlighted the initiative in Parliament, emphasizing the need to build technical capacity among youth and women from exploration to processing.
Tanzania Mahenge Graphite Project Map
Read More

Tanzania Mahenge Graphite Project Early Works to Complete by Mid-2026 Ahead of Final Investment Decision

Black Rock Mining's early works program at the Mahenge Graphite Project in Tanzania's Ulanga region is nearing completion, with final earthworks and resettlement activities expected to wrap up by late Q2 2026. Community compensation for the lower access road has been completed, the 220kV transmission line survey is finished, and all early works pricing has been validated against the 2022 FEED, positioning the project for a rapid construction ramp-up once full funding and a Final Investment Decision are secured.