Tanzania: 400 MW Power Plant Will Serve the Southern Region

Tanzania Electric Supply Company Ltd (Tanesco) and US-based Energy Firm; Symbion Power signed on 13 February 2013 a memorandum of understanding(MoU). The MoU is for the implementation of a 400 MW gas-fired power plant in Mtwara Region, in the south of Tanzania.

The MoU was signed by Tanesco Acting Managing Director; Mr Felchesmi Mramba and Symbion Chief Executive Officer; Mr Paul Hinks. It is a public-private partnership which takes advantage of the recent offshore commercial gas discovery in Tanzania.

The joint-venture project includes a 650 km transmission backbone from Mtwara to Songea. It will be connected to the national power grid through a line that will be built from Makambako to Songea.

Tanzania Investment Guide 2026 Free Edition

Implementation of the project will be phased, according to Mr Mramba, affirming that it will take three years from financial closure to completion.

Symbion and Tanesco will be working with a number of international funding agencies, banks and private equity firms this year in order to put the project’s financial package together. Noting, “many partners have already expressed great interest in the project”. We are hopeful that US government agencies such as the US Exim Bank and the US Overseas Private Investment Corporation will show keen interest in the investment too” affirmed Mr Hinks.

Southern regions in Tanzania have experienced poor power reliability for many years. Connecting southern regions to the national grid will significantly improve reliability of the entire electricity network.

Besides power supply, according to Tanesco and Symbion officials, the project would create jobs and incomes for millions of residents in the area.

Discussions on the project between the two partners started in September 2012 when Symbion presented the proposal to Tanesco and the Ministry of Energy and Minerals.

Tanzania Investment Guide 2026 Full Edition

From the signing of the MoU, it will take around 12 months to put the necessary financing in place before the three-year clock begins to tick, according to Symbion chief executive officer.

After completion of the engineering study and other ground works the total cost of the entire project will be known and publicly announced.

Want to know more about Energy in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Energy, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Related Posts
Tanzania Julius Nyerere Hydropower Project (JNHPP)
Read More

Tanzania Electricity Surplus Hits 2,375 MW As Julius Nyerere Hydropower Project Is Officially Launched

The Julius Nyerere Hydropower Project's 2,115MW plant lifted Tanzania's installed generation capacity to 4,646MW against peak demand of 2,271MW, with a surplus of 2,375MW, after President Samia Suluhu Hassan's inauguration on 22 August 2026. The government has signed an agreement to export power to Zambia and reached a trading arrangement with Kenya, while a newly completed 400kV Chalinze-Dodoma transmission line lifted national peak demand by 150MW within three days of coming online.
Presidents Samia Suluhu Hassan and Yoweri Museveni witness the Tanga Regional Energy Hub MoU signing, State House Dar es Salaam
Read More

Tanzania, Uganda Sign MoU for USD 20 Billion Tanga Energy Hub

Tanzania and Uganda signed a Memorandum of Understanding at State House on 6 August 2026 to develop Tanga as a Regional Energy Hub, a deal Tanzania's Energy Minister said could attract investment exceeding USD 20 billion. The agreement, signed by the Uganda National Oil Company, the Tanzania Petroleum Development Corporation, and Vitol Bahrain E.C., covers petroleum storage, refining, logistics, and distribution infrastructure at the port of Tanga, building on the East African Crude Oil Pipeline.
Samia Suluhu Hassan Africa50 Forum Dar es Salaam 2026
Read More

Tanzania President Calls for Faster Infrastructure Delivery Via PPPs as Country Signs Five Agreements on Power Transmission, Gas and Health

Tanzania President Samia Suluhu Hassan called for faster infrastructure delivery through public-private partnerships (PPPs) as Tanzania signed five agreements at Africa50's Infra for Africa Forum, covering an electricity transmission PPP with TANESCO, natural gas supply to local industry with TPDC and TAQA Arabia, and expanded kidney dialysis care. Africa50 secured USD 70 million in new capital from British International Investment, the Italian Climate Fund and Proparco, the private sector financing arm of the French Development Agency group (AFD).
Tanzania Contract 100 MW Kishapu Solar Project Phase Two
Read More

Tanzania Signs TZS 204.4 Billion Contract for 100 MW Kishapu Solar Project Phase Two

Tanzania has signed a contract worth approximately TZS 204.4 billion with Sagemcom Energy & Telecom SAS and STEG International Services for the 100 MW second phase of the Kishapu Solar Power Project in Ngunga, Shinyanga Region, taking the full 150 MW project's cost to approximately TZS 323 billion. The contract follows completion of the project's 50 MW first phase, which cost TZS 118.6 billion and became Tanzania's first grid-connected utility-scale solar plant in March 2026.