EACOP Secures First Financing Tranche for East African Crude Oil Pipeline Project

EACOP Ltd. has closed the first tranche of external financing for the $5 billion East African Crude Oil Pipeline. The funding, provided by a consortium of African and regional banks, will support the remaining construction phases of the Uganda-Tanzania pipeline, which is already 50% complete.

EACOP Ltd., the company responsible for the construction and future operation of the East African Crude Oil Pipeline (EACOP), has announced the successful closing of the first tranche of external financing for the project.

The financing is provided by a syndicate of financial institutions, including regional banks such as the African Export-Import Bank (Afreximbank), The Standard Bank of South Africa Limited, Stanbic Bank Uganda Limited, KCB Bank Uganda, and The Islamic Corporation for the Development of the Private Sector (ICD).

The EACOP project, with an estimated total cost of $5 billion, was initially funded through equity contributions from its shareholders following the Final Investment Decision (FID) in February 2022.

These contributions, made by TotalEnergies (62%), the Uganda National Oil Company Limited (UNOC – 15%), the Tanzania Petroleum Development Corporation (TPDC – 15%), and CNOOC (8%), enabled significant progress in the early stages of construction.

By the end of 2024, the project had surpassed 50% completion, with major milestones achieved in pipe haulage, infrastructure development, and workforce training.

The first tranche of external debt financing, announced in March 2025, will now fund the remaining phases of construction and operational setup.

Over 8,000 Ugandan and Tanzanian citizens are currently employed on the project, with approximately 400,000 man-hours of training provided to date.

Additionally, $500 million has been spent locally on goods and services, further contributing to the region’s economic development.

EACOP

The East African Crude Oil Pipeline is a world-class crude oil export infrastructure designed to transport Uganda’s crude oil from Kabaale in Hoima, Uganda, to the Chongoleani peninsula near Tanga, Tanzania, for export to international markets.

The pipeline will have a capacity of 246,000 barrels of crude oil per day and will span 1,443 kilometers, with 296 kilometers in Uganda and 1,147 kilometers in Tanzania.

The project includes six pumping stations, two pressure reduction stations, and a marine export terminal in Tanzania, which will feature a 3 MWp solar plant.

The pipeline will be insulated and buried, with power supplied primarily by hydro-based national grids.

Want to know more about Energy in Tanzania? Our free Tanzania Business and Investment Guide 2026 covers Energy, plus regulations, key sectors, and investment opportunities—all in one place.

Download Free Guide
Related Posts
Tanzania ASSESSMENT OF ECONOMIC IMPACTS ON TANZANIA ARISING FROM THE GULF CRISIS
Read More

Tanzania Gulf Crisis Report Rates Energy, Food, Transport, Tourism and Budget at High Risk

A May 2026 rapid assessment by Tanzania's National Planning Commission and UNDP rates energy, food, transport, tourism and the Government budget at high risk from the Gulf crisis, which raised Dar es Salaam fuel prices by up to 69% between January and May 2026. The report flags a possible TZS 153.7 billion monthly customs revenue shortfall and fuel subsidy needs rising to TZS 1,384.2 billion by July, alongside buffers including a 124% food self-sufficiency ratio, USD 6.3 billion in reserves and 57 trillion cubic feet of gas.
Tanzania-Rwanda energy cooperation agreement 2026 Hassan Kagame
Read More

Tanzania and Rwanda Sign Energy Cooperation Agreement Covering Power Trade, Oil, Gas and LNG

Tanzania and Rwanda signed a bilateral energy cooperation agreement covering cross-border electricity trade, joint power infrastructure development, and petroleum product distribution. The deal also extends to oil and gas exploration, LNG project opportunities, and the use of artificial intelligence in the energy sector, building on the existing 80 MW Rusumo interconnection, which has synchronized the grids of Tanzania, Rwanda, and Burundi since March 2024.
Russia Maxim Reshetnikov Tanzania Kitila Mkumbo
Read More

Tanzania and Russia Agree to Open Industry, Energy, and Infrastructure to Joint Investment

Tanzania and Russia have agreed to deepen investment cooperation in industry, energy, transport infrastructure, and air transport, with value-addition processing, production technology, and goods transportation named as priority areas at the Third Joint Intergovernmental Commission held in Arusha on 15–16 May 2026, which drew 120 Russian companies. The deals also cover Russian investment in mining, agriculture, and ICT, direct Air Tanzania (ATCL) flights to Russia, and a signed agreement to promote the Swahili language in Russia.