EACOP Secures First Financing Tranche for East African Crude Oil Pipeline Project

EACOP Ltd. has closed the first tranche of external financing for the $5 billion East African Crude Oil Pipeline. The funding, provided by a consortium of African and regional banks, will support the remaining construction phases of the Uganda-Tanzania pipeline, which is already 50% complete.

EACOP Ltd., the company responsible for the construction and future operation of the East African Crude Oil Pipeline (EACOP), has announced the successful closing of the first tranche of external financing for the project.

The financing is provided by a syndicate of financial institutions, including regional banks such as the African Export-Import Bank (Afreximbank), The Standard Bank of South Africa Limited, Stanbic Bank Uganda Limited, KCB Bank Uganda, and The Islamic Corporation for the Development of the Private Sector (ICD).

The EACOP project, with an estimated total cost of $5 billion, was initially funded through equity contributions from its shareholders following the Final Investment Decision (FID) in February 2022.

TANZANIA BUSINESS & INVESTMENT GUIDE 2026

These contributions, made by TotalEnergies (62%), the Uganda National Oil Company Limited (UNOC – 15%), the Tanzania Petroleum Development Corporation (TPDC – 15%), and CNOOC (8%), enabled significant progress in the early stages of construction.

By the end of 2024, the project had surpassed 50% completion, with major milestones achieved in pipe haulage, infrastructure development, and workforce training.

The first tranche of external debt financing, announced in March 2025, will now fund the remaining phases of construction and operational setup.

Over 8,000 Ugandan and Tanzanian citizens are currently employed on the project, with approximately 400,000 man-hours of training provided to date.

Additionally, $500 million has been spent locally on goods and services, further contributing to the region’s economic development.

EACOP

The East African Crude Oil Pipeline is a world-class crude oil export infrastructure designed to transport Uganda’s crude oil from Kabaale in Hoima, Uganda, to the Chongoleani peninsula near Tanga, Tanzania, for export to international markets.

The pipeline will have a capacity of 246,000 barrels of crude oil per day and will span 1,443 kilometers, with 296 kilometers in Uganda and 1,147 kilometers in Tanzania.

The project includes six pumping stations, two pressure reduction stations, and a marine export terminal in Tanzania, which will feature a 3 MWp solar plant.

The pipeline will be insulated and buried, with power supplied primarily by hydro-based national grids.

Related Posts
EACOP Q2 2025 Update
Read More

East Africa Crude Oil Pipeline Construction Reaches 72% Completion

The East Africa Crude Oil Pipeline project reached 72% completion as of Q3 2025, according to the latest company newsletter. Progress includes 800 km welded, over 300 km coated, and over 115 km lowered into the ground, alongside major works at pump stations, storage tanks, and the jetty in Tanga.