Construction of Tanzania Singida Gold Project Commenced

SINGIDA GOLD PROJECT CONSTRUCTION

Gold mining company Shanta Gold (AIM: SHG) recently announced that the construction of the Singida gold project is being commenced.

The Singida project is an open pit gold project covering an area of about 98 km2 located in the greenstone belt within the Ikungi district in the Singida region of central Tanzania.

Total capital investment in the project comes at USD 26 million over a 24-month construction period. The investment will be funded by Shanta’s internal cash flows.

Tanzania Investment Guide 2026 Free Edition

Expected annual production is projected at 32,000 ounces over an initial life of mine of seven years.

The Singida project currently employs 60 people, expected to increase to 300 at steady state production. Shanta is targeting a workforce comprising 100% of Tanzanian nationals.

Eric Zurrin, Chief Executive Officer, commented: “[…] Singida will have a major positive impact on the Ikungi region. Shanta intends to roll out its well-regarded CSR program into the surrounding villages which will lead to improvements in livelihoods, water, health and education.”

Tanzania Gold

Tanzania gold reserves are estimated at about 45 million ounces. Gold exploration has been centered mostly on the greenstone belts around Lake Victoria, where several large deposits have already been discovered and are being developed.

Tanzania’s gold production increased by more than 700% over the past 25 years, from 5 to 40-50 tonnes per year, while South Africa’s production of gold decreased from over 500 tonnes in 1990 to 117 tonnes in 2018.

Tanzania Investment Guide 2026 Full Edition

Current active gold mines include Buckreef, Bulyanhulu, Buzwagi, North Mara, Geita, New Luika, and Golden Pride.

Want to know more about Mining in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Mining, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Related Posts
Tanzania Samia Suluhu Hassan DRC Felix Tshisekedi
Read More

DRC to Build Dry Port in Dar es Salaam, Deepen Transport and Mining Ties with Tanzania

The Democratic Republic of the Congo (DRC) has begun preparations to build a dry port in Dar es Salaam that will provide customs, cargo handling, mineral certification, and quality control services for Congolese goods moving through Tanzania, President Félix Tshisekedi announced during a state visit to Tanzania on 18 August 2026. The DRC is among the largest users of Tanzanian ports, with approximately 7.2 million tonnes of cargo handled in 2023, as the two countries agreed to accelerate transport, trade, and mining cooperation along the Central Corridor.
Tanzania gold production 2025-2026
Read More

Tanzania Gold Production Reaches 67.8 Tonnes, Central Bank Buys 75.64%

Tanzania's Ministry of Minerals reported that the country produced 67.8 tonnes of gold worth TZS 18.4 trillion in the 2025/26 financial year, with 28,701 kilograms sold through five domestic refineries. The Bank of Tanzania purchased 21,710 kilograms, equivalent to 75.64% of that volume, under its Domestic Gold Purchase Programme to strengthen the country's foreign reserves.
North Rukwa Project helium licence map, Tanzania
Read More

Noble Helium Raises AUD 12 Million, Secures Rig for North Rukwa Drilling

Noble Helium Limited (ASX:NHE) raised AUD 12 million and converted AUD 6.603 million of debt to equity during the June 2026 quarter, ending with AUD 6.689 million in cash, according to its latest quarterly report. The company has contracted a rig to drill two wells at its Kinambo prospect within the North Rukwa Project in Tanzania, with mobilisation expected in August 2026.