East Africa Crude Oil Pipeline Construction Reaches 66.5% Completion

The East Africa Crude Oil Pipeline project reached 66.5% completion as of Q2 2025, according to the latest company newsletter. Progress includes 762 km welded, over 325 km coated, and over 104 km lowered, alongside major works at pump stations, storage tanks, and the jetty in Tanga.
EACOP Q2 2025 Update

The East African Crude Oil Pipeline (EACOP) project has reached 66.5% completion, according to the latest newsletter released by the company.

To date, 762 km of pipeline have been welded, more than 325 km coated, and over 104 km lowered into the ground.

The newsletter details the construction progress across all project components as of Q2 2025.

Tanzania Investment Guide 2026 Free Edition

Pipeline construction is ongoing across three lots: Lot 1 from Lake Albert in Uganda to the Mutukula border, Lot 2 from the border to Igugono in Singida, and Lot 3 from Igugono to Chongoleani in Tanga.

Since welding commenced in September 2024, 500 km of pipe have been welded, 200 km coated with Liquid Epoxy, and 54 km lowered into trenches.

Horizontal Directional Drilling works are advancing at the Sigi River, with casing and pipeline welding completed and reaming works progressing.

Main Camps and Pipe Yards are operational, with 11 camps accommodating 2,325 people. Activities include pipe delivery to the right-of-way, electrical installations, and environmental management such as food composting.

Progress has also been recorded at pump stations, where 30,220 cubic meters of priority concrete and 8,583 linear meters of underground piping have been completed.

TanzaniaInvest Capital Markets Report Banner

Pump Station 4 leads with 60% progress, followed by Pump Station 6 at 55% and Pump Station 3 at 47%. Work continues at other stations, with piping, steel structures, and installations underway.

At the Thermal Insulation Plant, inaugurated in March 2024, 787 km of pipes have been coated with polyurethane foam and 718 km dispatched for welding and stringing. Repairs of coating damage during transport are ongoing.

The marine terminal in Tanga has reached 33% completion, with seven out of eight site-fabricated storage tanks erected and storage tank works at 80% progress.

Tank A is undergoing hydrotesting, while other tanks are at different stages of welding and assembly.

Jetty construction is advancing, with 166 piles driven and 100 crossheads installed in shallow and deep water.

Prefabricated trestle modules have been installed, and work has commenced on the abutment in Chongoleani, Tanga.

The newsletter concludes that the groundwork for the delivery of First Oil is steadily taking shape, with pipeline welding, coating, and supporting infrastructure such as pump stations, terminals, and jetty works moving forward.

Want to know more about Energy in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Energy, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Free Newsletter

Get our monthly update on business and investment in Tanzania.

Related Posts
Mchechu OTR in talks with TAZAMA
Read More

Tanzania-Zambia Oil Pipeline Eyes Expansion as Lobito Corridor Raises Competition

The Tanzania-Zambia Mafuta (TAZAMA) Pipeline discussed strategic positioning and possible expansion in Tanzania with the Office of the Treasury Registrar (OTR). The talks come at a time when the regional petroleum transportation market is being influenced by alternative transportation infrastructure, such as the Lobito Corridor, with potential implications for the company's future business.
Songo Songo Offshore Gas
Read More

Tanzania’s Songo Songo Gas Field Sale to Taifa and Amber Goes to Appeal as Operator Plans to Stop Running the Field by 29 November

Taifa Gas and Amber Energy Investment appealed the Fair Competition Commission's 5 October 2026 block on the USD 10 Songo Songo gas field sale to the Fair Competition Tribunal on 20 October 2026. Operator PAET has rejected the government's licence extension terms as uneconomic and plans to stop operating the field, which Orca says supplies about 54% of Tanzania's daily gas output, by 29 November 2026.