Tanzania-Zambia 400kV Power Line 58% Completed

The Tanzania-Zambia power transmission project has reached 58% completion in Tanzania. The 400kV project includes 616 km of transmission lines and substations in Iringa, Mbeya, and Rukwa. It aims to connect Tanzania to Zambia and the Southern African Power Pool, enhancing regional power trade and supply reliability.
Tanzania - Zambia Interconnector

The construction of the 400kV Tanzania-Zambia (TAZA) power transmission project has reached 58% implementation on the Tanzanian side.

The progress was announced by Engineer Sadick Mwaifunga, Representative of the Commissioner for Electricity and Renewable Energy at the Ministry of Energy, during an inspection and evaluation visit involving officials from the Ministry, the Tanzania Electric Supply Company (TANESCO), and the World Bank.

The visit covered project sites in Iringa, Mbeya, and Rukwa regions, where works include the construction of a power transmission line from Kisada-Iringa, Iganjo-Mbeya, to the Malangali substation in Sumbawanga, as well as associated substations in the three regions.

Mwaifunga stated that the transmission line sections Iringa-Kisada, Kisada-Mbeya, Mbeya-Tunduma, and Tunduma-Sumbawanga have reached 81% completion, while the substations in Iringa, Kisada, Mbeya, Tunduma, and Sumbawanga are at 35%.

He further explained that the project will include a total of 1,614 towers carrying 400kV electricity. To date, over 420 towers have been installed, with work continuing.

Engineer Elias Makunga, TANESCO’s Project Manager, urged contractors to accelerate the works during the dry season to mitigate delays caused by the upcoming rainy season.

He emphasized that excuses related to weather disruptions would not be acceptable, stressing the importance of using the dry months to ensure the timely delivery of the project.

The World Bank commended the Ministry of Energy for effectively supervising the project and maintaining steady implementation progress.

Engineer Ananthan Pannerselvam, Project Manager for the contractor responsible for the Kisada-Iringa to Mbeya section, thanked the government for disbursing funds on time.

He confirmed that the works are progressing without major challenges and assured completion within the agreed timeframe.

The Tanzania-Zambia Power Interconnector

The project involves the construction a 620 km of 400 kV double circuit transmission line, from Iringa in the Southern Highlands of Tanzania, to the Zambian border, and continue on from the Zambian border to Sumbawanga.

This will link the Tanzanian grid to Zambia’s grid, and it includes the construction
of a sub-station at Tunduma, close to the Zambian border.

The project aims to strengthen regional energy trade, improve electricity supply reliability, and support economic growth by providing a stable power connection between the two countries and the Southern African Power Pool (SAPP).

The project is being implemented by TANESCO in collaboration with Zambia Electricity Supply Corporation (ZESCO), with financing from the World Bank, the African Development Bank, the European Union, and other partners. 

Want to know more about Energy in Tanzania? Our free Tanzania Business and Investment Guide 2026 covers Energy, plus regulations, key sectors, and investment opportunities — all in one place.

Download Free Guide
Related Posts
EACOP April 2026 Update
Read More

East African Crude Oil Pipeline Reaches 82% Completion

The East African Crude Oil Pipeline (EACOP) has reached 82% overall completion as of April 2026, with construction progressing across pipeline sections, pump stations, and the Chongoleani Marine Terminal in Tanga. The 1,443-kilometre pipeline is advancing steadily toward First Oil, with all line pipes delivered and the marine jetty at 88.1% completion.
Tanzania Mnazi Bay Gas Well
Read More

Tanzania Seeks Strategies to Revitalize Petroleum Exploration Activities

The Ministry of Energy instructed the Petroleum Upstream Regulatory Authority (PURA) and Tanzania Petroleum Development Corporation (TPDC) to seek strategies to revitalize petroleum exploration activities in Tanzania and add investment blocks. Officials highlighted the drop from 26 to 11 active Production Sharing Agreements and emphasized creating an enabling environment for exploration, including collaborations with Multi-Client Geophysical Companies.