Tanzania Ntorya Gas Pipeline Set for Q3 2026 Completion

The pipe to link the Ntorya gas field to the Madimba plant is manufactured and scheduled to arrive in Tanzania in late January 2026. This delivery allows for groundwork and pipelaying to commence immediately to meet the scheduled Q3 2026 completion and commissioning deadline.
Ntorya Ruvuma Tanzania Gas Field

Aminex plc (LSE: AEX) has announced that the necessary pipe for the link between the Ntorya gas field and the Madimba gas processing plant has been manufactured.

The materials are scheduled to arrive in Tanzania in late January 2026. Groundwork and pipelaying activities are set to commence immediately following the delivery of the equipment.

The completion and commissioning of the pipeline are scheduled for the third quarter of 2026.

Tanzania Investment Guide 2026 Free Edition

The operator, ARA Petroleum Tanzania (APT), is also in the advanced stages of the contracting process for all services required to bring the Ntorya-2 (NT-2) well into production.

The award of the principal contract for these production services is expected in January 2026 to align with the infrastructure timeline.

Furthermore, the procurement process for a drilling rig and associated services for the drilling of the Chikumbi-1 (CH-1) well and the workover of the Ntorya-1 (NT-1) well continues.

All tenders have been received by APT and are currently undergoing evaluation.

Essential equipment, including casings, tubulars, and wellheads for the CH-1 and NT-1 operations, is already secured on-site in Ntorya.

TanzaniaInvest Capital Markets Report Banner

A contract for civil works has been awarded to a local construction company to support the development of the field.

These works, starting in January 2026, include well pad preparation for CH-1, rehabilitation for NT-1 and NT-2, and the conversion of the Ntorya-3 site into the Ntorya Gas Field Base.

Preparation of the site for all upstream production facilities and ancillary access roads will also begin next month.

Charles Santos, Executive Chairman of Aminex commented: “Clearly, 2026 will mark the start of an exciting new chapter for Aminex and the beginning of a new era for Tanzania’s energy security and energy transition. Tanzania is on the cusp of a gas revival, which will fuel industrial and economic development while helping to improve Tanzanians’ living standards.”

The activities detailed above are supported by the 2026 work programme and budget which has been approved by the Tanzanian authorities.

The total budget for 2026 exceeds USD 50 million and covers all infrastructure and drilling milestones mentioned in the update.

Ntorya Gas Field & Madimba Processing Plant

The Ntorya gas field is located within the Ruvuma Basin in Southern Tanzania, a region central to the country’s onshore gas development strategy.

Seismic data acquired and exploration wells drilled in the area indicate a substantial natural gas resource estimated at around 1.6 trillion cubic feet (TCF).

Aminex plc holds a 25% non-operated interest in the Ruvuma Petroleum Sharing Agreement (PSA).

The project is operated by APT, which is managing the field’s transition to commercial production to supply the Madimba gas processing plant.

The 34.2-kilometre-long Ntorya–Madimba pipeline will transport raw natural gas from the Ntorya gas field to the Madimba processing plant.

Want to know more about Energy in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Energy, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Related Posts
Tanzania Julius Nyerere Hydropower Project (JNHPP)
Read More

Tanzania Electricity Surplus Hits 2,375 MW As Julius Nyerere Hydropower Project Is Officially Launched

The Julius Nyerere Hydropower Project's 2,115MW plant lifted Tanzania's installed generation capacity to 4,646MW against peak demand of 2,271MW, with a surplus of 2,375MW, after President Samia Suluhu Hassan's inauguration on 22 August 2026. The government has signed an agreement to export power to Zambia and reached a trading arrangement with Kenya, while a newly completed 400kV Chalinze-Dodoma transmission line lifted national peak demand by 150MW within three days of coming online.
Presidents Samia Suluhu Hassan and Yoweri Museveni witness the Tanga Regional Energy Hub MoU signing, State House Dar es Salaam
Read More

Tanzania, Uganda Sign MoU for USD 20 Billion Tanga Energy Hub

Tanzania and Uganda signed a Memorandum of Understanding at State House on 6 August 2026 to develop Tanga as a Regional Energy Hub, a deal Tanzania's Energy Minister said could attract investment exceeding USD 20 billion. The agreement, signed by the Uganda National Oil Company, the Tanzania Petroleum Development Corporation, and Vitol Bahrain E.C., covers petroleum storage, refining, logistics, and distribution infrastructure at the port of Tanga, building on the East African Crude Oil Pipeline.
Samia Suluhu Hassan Africa50 Forum Dar es Salaam 2026
Read More

Tanzania President Calls for Faster Infrastructure Delivery Via PPPs as Country Signs Five Agreements on Power Transmission, Gas and Health

Tanzania President Samia Suluhu Hassan called for faster infrastructure delivery through public-private partnerships (PPPs) as Tanzania signed five agreements at Africa50's Infra for Africa Forum, covering an electricity transmission PPP with TANESCO, natural gas supply to local industry with TPDC and TAQA Arabia, and expanded kidney dialysis care. Africa50 secured USD 70 million in new capital from British International Investment, the Italian Climate Fund and Proparco, the private sector financing arm of the French Development Agency group (AFD).
Tanzania Mini Small-Scale LNG Project
Read More

Tanzania Signs Agreements for First Small-Scale LNG Project To Extend Natural Gas Access to Arusha, Dodoma, Mwanza, and Zanzibar

The Tanzania Petroleum Development Corporation (TPDC), TAQA Arabia subsidiary Rosetta Energy Solutions, and Africa50 have signed agreements for a USD 100 million small-scale LNG project, targeting commercial operations by 2027. The project will extend gas distribution to Arusha, Dodoma, Mwanza, and Zanzibar, areas currently outside Tanzania's pipeline network, with TPDC seeking a stake exceeding 30% in the venture.