Tanzania to Receive USD 123 million for Power Transmission Project in Northwest

POWER DISTRIBUTION LINE NYAKANAZ KIGOMA

The African Development Bank (AfDB) approved on Friday 20 July 2018, a loan of USD 123.39 million to the Government of Tanzania to finance part of the country’s North- West Grid 400 kV Nyakanaz – Kigoma power transmission line project.

The project will be completed by 2024. It involves the Construction of a 280-km 400 KV transmission line from Nyakanazi to Kigoma; Extension of Nyakanazi substation and construction of a new substation at Kigoma; Integration of existing Kigoma and Kasulu 33 KV distribution networks with the main grid including supply of last-mile connection materials to serve at-least 10,000 new consumers in Kigoma Region.

The project aims to improve supply, reliability and affordability of electricity in Kigoma Region in North-western Tanzania by providing main grid access for the socio-economic transformation of the region in line with Tanzania Vision 2025.

Tanzania Investment Guide 2026 Free Edition

It will increase electricity access from 16.2% to 20% in the region with over 483,000 households by 2024.

The project will lower energy production costs by decommissioning expensive diesel-powered plants in Kigoma and Kasulu urban centres including surrounding areas. In addition to enhancing job creation, the project will reduce greenhouse gas emissions in northwestern Tanzania.

Furthermore, it will complement the ongoing Bank-funded 220 kV Rusumo-Nyakanazi regional transmission line including the multinational 80 MW Rusumo Hydro Power Plant as well as other Development Partner supported energy infrastructure programmes in northwestern Tanzania.

The North-West Grid transmission line project is aligned with the Bank’s Ten Year Strategy (2012 – 2022) and the High Five priorities, especially “Light-up & Power Africa” and New Deal on Energy for Africa which aim to achieve Universal Access to Energy in regional member countries. Also, the project is in line with the Bank’s Tanzania Country Strategy Paper (2016-2020) which focuses on infrastructure development.

The project will be financed from three sources: the AfDB loan (contributing 66%), South Korea Economic Development Co-operation Fund (contributing 24%), and the Government of Tanzania (contributing 10%), for an overall cost estimated at USD186.12 million.

TanzaniaInvest Capital Markets Report Banner

Tanzania Rural Electrification

According to the National Census of 2012, about 70% of Tanzanians reside in rural areas whereas only 7% of the rural population is connected to electricity supply.

This is why the Government of Tanzania plans to increase rural connection levels to 50% by 2025 and at least 75% by 2033.

To achieve these targets, more funds will be required for generation, transmission and distribution systems expansion.

Want to know more about Energy in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Energy, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Free Newsletter

Get our monthly update on business and investment in Tanzania.

Related Posts
Mchechu OTR in talks with TAZAMA
Read More

Tanzania-Zambia Oil Pipeline Eyes Expansion as Lobito Corridor Raises Competition

The Tanzania-Zambia Mafuta (TAZAMA) Pipeline discussed strategic positioning and possible expansion in Tanzania with the Office of the Treasury Registrar (OTR). The talks come at a time when the regional petroleum transportation market is being influenced by alternative transportation infrastructure, such as the Lobito Corridor, with potential implications for the company's future business.
Songo Songo Offshore Gas
Read More

Tanzania’s Songo Songo Gas Field Sale to Taifa and Amber Goes to Appeal as Operator Plans to Stop Running the Field by 29 November

Taifa Gas and Amber Energy Investment appealed the Fair Competition Commission's 5 October 2026 block on the USD 10 Songo Songo gas field sale to the Fair Competition Tribunal on 20 October 2026. Operator PAET has rejected the government's licence extension terms as uneconomic and plans to stop operating the field, which Orca says supplies about 54% of Tanzania's daily gas output, by 29 November 2026.