ICSID Dismisses Two of Tanzania’s Three Appeals in Ntaka Nickel Project Case, Total Compensation Increases to $120 M

Ntaka Hill Nickel Project

In the latest development about the Ntaka Hill Nickel Project, the International Centre for Settlement of Investment Disputes (ICSID) has made a crucial decision regarding the United Republic of Tanzania’s request to annul a substantial arbitration award.

The award, which was initially decided in July 2023, ordered Tanzania to compensate Indiana Resources Limited and its associated entities over USD 109.5 million for the unlawful expropriation of the Ntaka Hill Nickel Project.

The ICSID, a division of the World Bank, has now ruled that the majority of Tanzania’s grounds for annulment of the award are “manifestly without legal merit.”

This decision significantly narrows the scope of Tanzania’s challenge to the original ruling, which found the country in violation of the UK-Tanzania Bilateral Investment Treaty (BIT) due to its actions against the Ntaka Hill Nickel Project.

In a detailed press release, Indiana Resources Limited (ASX: IDA) revealed that two out of three grounds for annulment presented by Tanzania were struck down by the ad hoc Committee.

These included allegations of the Tribunal’s manifest excess of powers, failure to state reasons for the award, and a serious departure from a fundamental rule of procedure regarding cost allocation.

The proceedings will now focus solely on the remaining complaint concerning procedural departures.

The total compensation, including damages, additional losses, and accrued interest, now stands at USD 120 million, with interest continuing to accrue at approximately USD 1 million per month. This financial burden highlights the significant stakes involved as Tanzania navigates its next steps in the legal battle.

Bronwyn Barnes, Executive Chairman of Indiana Resources, expressed optimism following the Committee’s decision, urging Tanzania to recognize the futility of further delays and fulfill its compensation obligations.

This sentiment echoes her previous satisfaction with the Tribunal’s decision in July 2023, marking a consistent stance on seeking justice for the expropriation of the Ntaka Hill Nickel Project.

The Ntaka Hill Nickel Project

The Ntaka Hill Nickel Project is a development-ready advanced nickel sulfide project in southern Tanzania with estimated Mineral Resources of 56.2mt @ 0.63% Ni, 0.14% Cu, 0.02% Co for 356,380t of contained nickel1, JORC (2012).

Indiana is the major shareholder of Ntaka Nickel Holdings Ltd and Nachingwea UK Ltd (both incorporated in the United Kingdom) which historically held the licenses for the Ntaka Hill Nickel Project through its 100% owned subsidiary Nachingwea Nickel Ltd. 

The project became the center of international arbitration after the Tanzanian government, under the administration of former President Magufuli, abolished the Retention Licence without offering a replacement classification. This led to the project’s expropriation in January 2018, sparking the legal challenge that culminated in the ICSID’s ruling.

Indiana actively engaged with Tanzanian authorities to resolve the matter but was unsuccessful in reinstating the Project Licence.

Want to know more about Mining in Tanzania? Our free Tanzania Business and Investment Guide 2026 covers Mining, plus regulations, key sectors, and investment opportunities—all in one place.

Download Free Guide
Related Posts
Tanzania steel plant Dodoma
Read More

TZS 600 Billion Steel Plant Using Local Iron Ore to Be Developed in Dodoma, Work Starts in July 2026

A1 Iron & Steel Tanzania Ltd plans to invest TZS 600 billion in a new steel manufacturing plant in Nala, Dodoma. The project will use iron ore as its main raw material, and support Tanzania's strategy to increase mineral value addition and reduce dependence on imported steel products. Construction is scheduled to begin in July 2026 and is expected to be completed within 15 months.
Tanzania Anthony Mavunde Kitila Mkumbo Small-Scale Miners Recommendations Report
Read More

Tanzania Plans Mining Fund and Credit Guarantees to Support Small-Scale Miners

The Government of Tanzania has received recommendations aimed at strengthening the small-scale mining sector through improved access to finance, technology, and geological information. The proposals include establishing a mining fund, expanding credit guarantees, and supporting mineral research to increase employment, reduce poverty, and boost economic growth.
Kabanga Nickel Deposit
Read More

USD 942M Kabanga Nickel Project Moves Closer to Implementation, FID Expected in 2026

The Kabanga Nickel Project has moved closer to implementation after Lifezone Metals (NYSE: LZM) Executive Chairman Keith Liddell and Treasury Registrar Nehemiah Mchechu briefed President Samia Suluhu Hassan on 8 June 2026, with both sides confirming an agreed project structure and turning to finalise the refinery and beneficiation component. The USD 942 million project is targeting a final investment decision in 2026 and is expected to generate USD 2.4 billion in corporate income taxes and around 1,090 jobs.
Lindi Jumbo and Tanzanian government sign graphite joint venture in Ruangwa, Lindi
Read More

Tanzania Government Secures 16% Stake in Lindi Jumbo Graphite Mine Through Ndovu Graphite Joint Venture

The Tanzanian government has formalized its statutory 16% non-dilutable equity stake in the Lindi Jumbo graphite mine in Lindi Region through a joint venture agreement that creates Ndovu Graphite Limited, with Lindi Jumbo Limited retaining an 84% stake. The mine produces 40,000 tonnes of graphite per year over a 24-year mine life, and Tanzania currently ranks sixth globally in graphite production, with an annual output of 25,000 tonnes from two large-scale operating mines, Lindi Jumbo and God Mwanga, in Tanga.