ICSID Dismisses Two of Tanzania’s Three Appeals in Ntaka Nickel Project Case, Total Compensation Increases to $120 M

Ntaka Hill Nickel Project

In the latest development about the Ntaka Hill Nickel Project, the International Centre for Settlement of Investment Disputes (ICSID) has made a crucial decision regarding the United Republic of Tanzania’s request to annul a substantial arbitration award.

The award, which was initially decided in July 2023, ordered Tanzania to compensate Indiana Resources Limited and its associated entities over USD 109.5 million for the unlawful expropriation of the Ntaka Hill Nickel Project.

The ICSID, a division of the World Bank, has now ruled that the majority of Tanzania’s grounds for annulment of the award are “manifestly without legal merit.”

Tanzania Investment Guide 2026 Free Edition

This decision significantly narrows the scope of Tanzania’s challenge to the original ruling, which found the country in violation of the UK-Tanzania Bilateral Investment Treaty (BIT) due to its actions against the Ntaka Hill Nickel Project.

In a detailed press release, Indiana Resources Limited (ASX: IDA) revealed that two out of three grounds for annulment presented by Tanzania were struck down by the ad hoc Committee.

These included allegations of the Tribunal’s manifest excess of powers, failure to state reasons for the award, and a serious departure from a fundamental rule of procedure regarding cost allocation.

The proceedings will now focus solely on the remaining complaint concerning procedural departures.

The total compensation, including damages, additional losses, and accrued interest, now stands at USD 120 million, with interest continuing to accrue at approximately USD 1 million per month. This financial burden highlights the significant stakes involved as Tanzania navigates its next steps in the legal battle.

Tanzania Investment Guide 2026 Full Edition

Bronwyn Barnes, Executive Chairman of Indiana Resources, expressed optimism following the Committee’s decision, urging Tanzania to recognize the futility of further delays and fulfill its compensation obligations.

This sentiment echoes her previous satisfaction with the Tribunal’s decision in July 2023, marking a consistent stance on seeking justice for the expropriation of the Ntaka Hill Nickel Project.

The Ntaka Hill Nickel Project

The Ntaka Hill Nickel Project is a development-ready advanced nickel sulfide project in southern Tanzania with estimated Mineral Resources of 56.2mt @ 0.63% Ni, 0.14% Cu, 0.02% Co for 356,380t of contained nickel1, JORC (2012).

Indiana is the major shareholder of Ntaka Nickel Holdings Ltd and Nachingwea UK Ltd (both incorporated in the United Kingdom) which historically held the licenses for the Ntaka Hill Nickel Project through its 100% owned subsidiary Nachingwea Nickel Ltd. 

The project became the center of international arbitration after the Tanzanian government, under the administration of former President Magufuli, abolished the Retention Licence without offering a replacement classification. This led to the project’s expropriation in January 2018, sparking the legal challenge that culminated in the ICSID’s ruling.

Indiana actively engaged with Tanzanian authorities to resolve the matter but was unsuccessful in reinstating the Project Licence.

Want to know more about Mining in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Mining, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Related Posts
North Rukwa Project helium licence map, Tanzania
Read More

Noble Helium Raises AUD 12 Million, Secures Rig for North Rukwa Drilling

Noble Helium Limited (ASX:NHE) raised AUD 12 million and converted AUD 6.603 million of debt to equity during the June 2026 quarter, ending with AUD 6.689 million in cash, according to its latest quarterly report. The company has contracted a rig to drill two wells at its Kinambo prospect within the North Rukwa Project in Tanzania, with mobilisation expected in August 2026.
Tanzania Mineral Testing Laboratory Dodoma 3d plan
Read More

Dodoma Mineral Testing Laboratory on Track for September 2027 Completion

The Geological Survey of Tanzania (GST) says construction of its Dodoma mineral testing laboratory in Kizota, Dodoma, is progressing on schedule, with completion set for September 2027, a year after Minister for Minerals Anthony Mavunde laid the foundation stone in August 2025. The TZS 14.3 billion (approx. USD 5.4 million) facility is expected to become the largest of its kind in East and Central Africa, offering internationally accredited testing services and easing long-standing sample-analysis delays for artisanal and small-scale miners.
IMF Tanzania flag
Read More

IMF Approves USD 443.9 Million for Tanzania, Projects 6.2% GDP Growth Supported by Mining, Agriculture, and Tourism

The IMF Executive Board has approved an immediate disbursement of USD 443.9 million to Tanzania after completing the final reviews under the Extended Credit Facility and Resilience and Sustainability Facility programmes. The IMF said Tanzania maintained strong economic growth and macroeconomic stability while highlighting the need for continued reforms and fiscal consolidation.
Tanzania Grinding-Ball
Read More

Chinese Company to Build Grinding-Ball Factory at Buzwagi SEZ

China's Oriental Casting and Forging Ltd plans to establish a factory for steel grinding balls and other mining consumables at the Buzwagi Special Economic Zone in Kahama, Shinyanga, following a meeting between Minister of Minerals Anthony Mavunde and the company's managing director Hou Songcun. The project is part of Tanzania's push to manufacture mining consumables locally, cut import dependence and position itself as a regional supply hub, though no investment value or job figures have been disclosed.