Tanzania Signs USD 105.6 Million Contracts to Connect Kagera Region to National Grid in 24 Months

The Tanzanian government has signed USD 105.6 million contracts to connect Kagera Region to the national grid for the first time. The project includes a 220 kV transmission line from Benako to Kyaka and a 220/33 kV substation, ensuring reliable electricity for over 3 million residents across multiple districts.
Tanzania Kagera Region contract electricity grid connection

The Government of Tanzania has signed contracts worth USD 105.6 million to connect Kagera Region to the national electricity grid for the first time.

The project involves the construction of a 220 kV transmission line from Benako in Ngara District to Kyaka in Misenyi District, and a 220/33 kV substation at Benako. It will be completed within 24 months at a total cost of TZS 262.5 billion.

The contracts were awarded to China’s TBEA Co. Ltd for the substation construction and India’s Transrail Lighting Limited for the transmission line.

Tanzania Investment Guide 2026 Free Edition

All districts of Kagera, including Bukoba, Muleba, Misenyi, Karagwe, and Kyerwa, will be supplied with reliable power from the national grid.

Until now, the region has relied mainly on electricity imports from Uganda, totaling around 40 MW, and an additional 7 MW from a private operator.

Speaking at the signing ceremony in Dodoma on 25 August 2025, Deputy Prime Minister and Minister of Energy Doto Biteko said the project fulfills President Samia Suluhu Hassan’s commitment to deliver stable power to the region.

“For the first time, Kagera will be connected to the national grid, guaranteeing reliable electricity supply and enabling economic and social development across the region,” Biteko said. He confirmed the project is to be implemented within 24 months.

The project is co-financed by development partners, with the OPEC Fund contributing USD 60 million, the Abu Dhabi Fund USD 30 million, and the Saudi Fund USD 13 million.

Tanzania Investment Guide 2026 Full Edition

The Government of Tanzania will contribute USD 2.6 million to cover compensation for more than 1,000 residents affected by the project.

Kagera Regional Commissioner Fatuma Mwassa welcomed the development, noting that previously only three districts in the region were connected to the grid.

She said the connection will unlock economic opportunities and pledged that residents will pay their electricity bills to support TANESCO’s operations.

Permanent Secretary of the Ministry of Energy Felchesmi Mramba said that with this project, all four Tanzanian regions that were not yet connected to the national grid are now covered by grid-extension projects.

TANESCO Managing Director Lazaro Twange added that the project will enable integration of new generation projects, including the 87 MW Kakono hydropower plant.

Kagera Region

Kagera Region is located in northwestern Tanzania, on the western shore of Lake Victoria, and shares borders with Uganda, Rwanda, and Burundi.

The region has a population of more than 3 million people and covers several districts, including Bukoba, Muleba, Misenyi, Karagwe, and Kyerwa.

The economy of Kagera is primarily agricultural, with major production of coffee, tea, bananas, and fisheries products, supporting both local consumption and cross-border trade.

Despite its economic potential, until recently, the majority of districts in the region relied on electricity imports from Uganda, totaling around 40 MW, while a small portion received an additional 7 MW from a private operator at Mirongo/Kikagati.

Prior to the current project, only three districts in Kagera were connected to the national electricity grid, leaving the rest of the region without access to reliable national power.

Want to know more about Energy in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Energy, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Related Posts
Tanzania Julius Nyerere Hydropower Project (JNHPP)
Read More

Tanzania Electricity Surplus Hits 2,375 MW As Julius Nyerere Hydropower Project Is Officially Launched

The Julius Nyerere Hydropower Project's 2,115MW plant lifted Tanzania's installed generation capacity to 4,646MW against peak demand of 2,271MW, with a surplus of 2,375MW, after President Samia Suluhu Hassan's inauguration on 22 August 2026. The government has signed an agreement to export power to Zambia and reached a trading arrangement with Kenya, while a newly completed 400kV Chalinze-Dodoma transmission line lifted national peak demand by 150MW within three days of coming online.
Presidents Samia Suluhu Hassan and Yoweri Museveni witness the Tanga Regional Energy Hub MoU signing, State House Dar es Salaam
Read More

Tanzania, Uganda Sign MoU for USD 20 Billion Tanga Energy Hub

Tanzania and Uganda signed a Memorandum of Understanding at State House on 6 August 2026 to develop Tanga as a Regional Energy Hub, a deal Tanzania's Energy Minister said could attract investment exceeding USD 20 billion. The agreement, signed by the Uganda National Oil Company, the Tanzania Petroleum Development Corporation, and Vitol Bahrain E.C., covers petroleum storage, refining, logistics, and distribution infrastructure at the port of Tanga, building on the East African Crude Oil Pipeline.
Samia Suluhu Hassan Africa50 Forum Dar es Salaam 2026
Read More

Tanzania President Calls for Faster Infrastructure Delivery Via PPPs as Country Signs Five Agreements on Power Transmission, Gas and Health

Tanzania President Samia Suluhu Hassan called for faster infrastructure delivery through public-private partnerships (PPPs) as Tanzania signed five agreements at Africa50's Infra for Africa Forum, covering an electricity transmission PPP with TANESCO, natural gas supply to local industry with TPDC and TAQA Arabia, and expanded kidney dialysis care. Africa50 secured USD 70 million in new capital from British International Investment, the Italian Climate Fund and Proparco, the private sector financing arm of the French Development Agency group (AFD).
Tanzania Contract 100 MW Kishapu Solar Project Phase Two
Read More

Tanzania Signs TZS 204.4 Billion Contract for 100 MW Kishapu Solar Project Phase Two

Tanzania has signed a contract worth approximately TZS 204.4 billion with Sagemcom Energy & Telecom SAS and STEG International Services for the 100 MW second phase of the Kishapu Solar Power Project in Ngunga, Shinyanga Region, taking the full 150 MW project's cost to approximately TZS 323 billion. The contract follows completion of the project's 50 MW first phase, which cost TZS 118.6 billion and became Tanzania's first grid-connected utility-scale solar plant in March 2026.