East Africa Crude Oil Pipeline Construction Reaches 72% Completion

The East Africa Crude Oil Pipeline project reached 72% completion as of Q3 2025, according to the latest company newsletter. Progress includes 800 km welded, over 300 km coated, and over 115 km lowered into the ground, alongside major works at pump stations, storage tanks, and the jetty in Tanga.
EACOP Q2 2025 Update

The East African Crude Oil Pipeline (EACOP) project has reached 72% completion, according to the latest newsletter released by the company covering Q3 of 2025.

Pipeline Progress Summary

Pipeline construction activities are progressing across all 3 lots during Quarter 3.

Lot 1: Lake Albert, Bullisa District, Uganda to Mutukula Boarder, Kyotera District, Uganda.

Lot 2: Mutukula Boarder, Kyotera District Uganda, to Igugono, Singida Region, Tanzania.

Lot 3: Igugono, Singida Region Tanzania, to Chongoleani, Tanga Region Tanzania.

To date, 800 km of pipeline has been welded, 300 km coated with Liquid Epoxy, and 115 km lowered into the ground. Works commenced for the installation of High high-voltage cables along the pipeline route.

Horizontal Directional Drilling (HDD) at the Sigi River is ongoing, 38-inch, 44-inch and 50-inch reaming works were completed during the quarter, and works commenced for the 54-inch reaming in preparation for the pipe to be pulled through.

Marine Terminal & Tanks Progress Summary

Marine Terminal progress is at 38.5%. Works commenced for the erection of steel structures of the Power Generator Building. Nitrogen and Deluge Skids were installed on foundations.

Storage Tanks progress is at 83%. Tank A completed hydrotesting and was ready for dewatering into Tank B.

Tank B completed roof drainage system welding, and the pre-Hydrotest punch list was cleared. Preparation is ongoing for the hydrotest to commence.

Tank C floating roof plates and attachments welding is ongoing. Tank D is finalising the erection and welding of floating roof attachments, piping erection, and welding works commenced.

Jetty Progress Summary

The Jetty is the pipeline marine export terminal infrastructure at the Tanga Port in Tanzania, which will serve as the offshore loading facility where crude oil transported through EACOP will be loaded into crude oil export tankers.

The construction of the Jetty achieved significant milestones in Quarter 3 with the launching girder completing piling activities in the shallow area and the completion of trestle installations in the deep area.

180 piles and 110 crossheads had been installed in the deeper and shallower water. Pre-fabricated modules to form the trestle are also being installed in the deep and shallow water. At the end of the quarter, 97 modules had been installed.

At the Abutment in Chongoleani, concrete casting was completed for Bents 95 to 99. Rock placing is ongoing.

Commenting on the progress, John Bosco Habumugisha, General Manager Uganda for EACOP, wrote in his message: “The period from July to September has been marked by steady advancement across our operations. In this past quarter, we have deepened our collaboration with local communities, reinforced our environmental and safety commitments, and remained focused on ensuring that every step forward brings long-term benefits to the people of Uganda and Tanzania and the East African Region.”

Want to know more about Energy in Tanzania? Our free Tanzania Business and Investment Guide 2026 covers Energy, plus regulations, key sectors, and investment opportunities—all in one place.

Download Free Guide
Related Posts
Tanzania-Rwanda energy cooperation agreement 2026 Hassan Kagame
Read More

Tanzania and Rwanda Sign Energy Cooperation Agreement Covering Power Trade, Oil, Gas and LNG

Tanzania and Rwanda signed a bilateral energy cooperation agreement covering cross-border electricity trade, joint power infrastructure development, and petroleum product distribution. The deal also extends to oil and gas exploration, LNG project opportunities, and the use of artificial intelligence in the energy sector, building on the existing 80 MW Rusumo interconnection, which has synchronized the grids of Tanzania, Rwanda, and Burundi since March 2024.
Russia Maxim Reshetnikov Tanzania Kitila Mkumbo
Read More

Tanzania and Russia Agree to Open Industry, Energy, and Infrastructure to Joint Investment

Tanzania and Russia have agreed to deepen investment cooperation in industry, energy, transport infrastructure, and air transport, with value-addition processing, production technology, and goods transportation named as priority areas at the Third Joint Intergovernmental Commission held in Arusha on 15–16 May 2026, which drew 120 Russian companies. The deals also cover Russian investment in mining, agriculture, and ICT, direct Air Tanzania (ATCL) flights to Russia, and a signed agreement to promote the Swahili language in Russia.
Tanzania Kenya Rwanda
Read More

Tanzania Hosts Rwanda and Kenya Presidents, Signs MoUs on Tanga-Taveta SGR, Dar-Mombasa Gas Pipeline, and Scraps Non-Tariff Barriers

Tanzania hosted Rwandan President Paul Kagame on 3 May 2026 and Kenyan President William Ruto on 4-5 May 2026, signing eight MoUs with Kenya covering railways and a Dar es Salaam-Mombasa gas pipeline study, and agreeing to eliminate all non-tariff barriers by May 2026. Bilateral trade with Rwanda reached TZS 644 billion in 2025, while Tanzania-Kenya trade stood at over USD 720 million in 2024.