US$523M Approved for Tanzania’s Nyanzaga Gold Project Development

Perseus Mining has approved a US$523M investment to proceed with the development of the Nyanzaga Gold Project in Tanzania, targeting first gold by Q1 2027. The decision follows an updated feasibility study and continued cooperation with the Tanzanian government.
Tanzania Nyanzaga Gold Project map

Perseus Mining Limited (ASX/TSX: PRU) announced on 28 April 2025 that it has made a Final Investment Decision (FID) to proceed with the development of the Nyanzaga Gold Project in northwest Tanzania’s Mwanza Region, near Lake Victoria.

Perseus Mining is an Australian-based gold producer and developer operating in West Africa, with producing assets in Ghana and Côte d’Ivoire.

The company will invest approximately US$523 million, including contingency, to construct and prepare the project for production, with the first gold pour expected in Q1 2027.

The development will be fully financed through interest-free, intercompany loans from Perseus’s existing cash and bullion reserves, which totalled US$801 million as of 31 March 2025.

Ahead of the FID, Perseus had already invested US$27.5 million to build project team capacity and initiate early works, including site establishment, temporary accommodation for construction personnel, bulk earthworks, and implementation of the Relocation Action Plan to provide housing for affected communities.

The updated feasibility study reflects a decision to pursue a large-scale, fully open-pit mining operation, diverging from a previously proposed smaller-scale, combined open-pit and underground model.

The Nyanzaga Gold Project is projected to produce 2.01 million ounces of gold over an 11-year Phase 1 mine life, based on a JORC 2012 Probable Ore Reserve of 52.0 Mt at 1.40 g/t gold for 2.3 Moz.

Annual gold production is expected to average over 200,000 ounces from FY28 to FY35, with peak output of 246,000 ounces forecast for FY28.

The estimated All-In Site Cost (AISC) over the life of the mine is US$1,211/oz.

Capital costs include US$472 million for plant and infrastructure, plus US$51 million in pre-production capital, totalling US$523 million.

At a gold price of US$2,100/oz, the project’s estimated post-tax NPV (10%) is US$202 million with an IRR of 19%.

At a higher gold price scenario of US$2,700/oz, post-tax NPV increases to US$617 million with an IRR of 34%.

Perseus noted that the decision builds on its track record of successfully developing and operating gold mines in Africa, including Edikan, Sissingué, and Yaouré, the latter completed ahead of schedule and under budget in 2020.

The FID follows constructive discussions with the Government of Tanzania to finalise the existing Framework Agreement and Shareholders’ Agreement governing the project.

Want to know more about Mining in Tanzania? Our free Tanzania Business and Investment Guide 2026 covers Mining, plus regulations, key sectors, and investment opportunities — all in one place.

Download Free Guide
Related Posts
Tanzania Mahenge Graphite Project Map
Read More

Tanzania Mahenge Graphite Project Early Works to Complete by Mid-2026 Ahead of Final Investment Decision

Black Rock Mining's early works program at the Mahenge Graphite Project in Tanzania's Ulanga region is nearing completion, with final earthworks and resettlement activities expected to wrap up by late Q2 2026. Community compensation for the lower access road has been completed, the 220kV transmission line survey is finished, and all early works pricing has been validated against the 2022 FEED, positioning the project for a rapid construction ramp-up once full funding and a Final Investment Decision are secured.
Tanzania Panda Hill Niobium Agreement Signing
Read More

Tanzania Signs Niobium Project Agreement Targeting 4% of Global Output

The Government of Tanzania and Panda Hill Tanzania Limited have officially signed an agreement to advance the Panda Hill niobium project in Mbeya. The deal formalizes government participation through a 16% free carried interest, positions Tanzania to contribute 4% of global niobium supply, and includes the construction of a ferroniobium plant, local value addition, and thousands of jobs over the project’s life.