New Gold Mining Company In Mara Region To Start Production In Q2-2016

mara-gold-mining

CATA Mining Company Limited, a Tanzanian-Canadian gold exploration and production company, has recently inaugurated a new gold mine in Butiama district in the country’s Mara region that has met all standard requirements and is ready to start production by the end of Q2-2016.

Construction works started in 2015 and represented a total investment of USD 54 million financed through a loan provided by CRDB Bank and TIB Development Bank.

According to CATA Mining Director, Mr. Mahuza Mumangi Nyakirang’ani, the funds have been exclusively used for setting up the middle-sized gold mine to get it ready to start production on the scheduled date and already 200 people are being employed at its facilities.

CATA Mining Gold Mine Project Manager, Mr. Peter Bourhill, explained that all workers are from surrounding villages and that despite production has not started, it is already helping communities with improvement of their transport and education facilities.

In this regard, the company asked for the support of Tanzania’s Minister of Energy and Minerals, Prof. Sospeter Muhongo, to provide the mine with electricity and save the funds that are being used to supply it with diesel as energy source when it can be used to further enhance villages’ infrastructure, Mr. Nyakirang’ani added.

CATA Mining is the first mine using modern and advance technology in the area and the population should give them the necessary support to boost production and get better employment alternatives instead of constraining them, explained Minister Muhongo.

Mara is known in Tanzania for its richness in gold resources due to a good performance from North Mara mine operated by Acacia Mining Plc (LSE:ACA, DSE:ACA), which in Q4-2015 reached a total gold production of 77,304 ounces that was 9% higher than in Q4-2014 and with a 9% higher head grade of 8.7 grams of gold per tonne up from 7.9 grams per tonne in the same periods.

Tanzania currently ranks 15th in the world and 3rd in Africa in terms of gold production with a total of 50.8 tonnes -1,791,917 ounces- last year behind South Africa with 167.9 tonnes and Ghana with 104.1 tonnes in the same period according to the world gold council.

The country has an estimated of 45 million ounces of gold reserves and the sector is expected to grow at a rate of 7.7% per annum in the short term according to the Tanzania Chamber of Minerals and Energy (TCME).

Want to know more about Mining in Tanzania? Our free Tanzania Business and Investment Guide 2026 covers Mining, plus regulations, key sectors, and investment opportunities — all in one place.

Download Free Guide
Related Posts
Anthony Mavunde Parliament Bunge
Read More

Tanzania’s 2026/27 Mining Budget Sets Ambition for Critical Minerals Leadership and Top-4 Global Niobium Producer Status

Tanzania's Ministry of Minerals has tabled a TZS 174.98 billion budget for FY 2026/27, with a revenue collection target of TZS 1.41 trillion from a sector whose GDP contribution has climbed to 11.9% and whose exports rose 31.1% to USD 5,401.9 million in 2025. The budget prioritises critical and strategic minerals, the Panda Hill niobium project expected to make Tanzania a top-4 global producer, the Buzwagi value-addition hub, and expanding geophysical survey coverage to 50% of the country by 2030.
Tanzania mineral processing
Read More

Tanzania to Build Mineral Processing Center in Shinyanga to Boost Value Addition

The Tanzanian government plans to establish a Mineral Processing Center in Mwakitolyo, Shinyanga Region, to deepen mineral value addition and expand local participation in the mineral value chain. Deputy Minister for Minerals Dr. Steven Kiruswa highlighted the initiative in Parliament, emphasizing the need to build technical capacity among youth and women from exploration to processing.
Tanzania Mahenge Graphite Project Map
Read More

Tanzania Mahenge Graphite Project Early Works to Complete by Mid-2026 Ahead of Final Investment Decision

Black Rock Mining's early works program at the Mahenge Graphite Project in Tanzania's Ulanga region is nearing completion, with final earthworks and resettlement activities expected to wrap up by late Q2 2026. Community compensation for the lower access road has been completed, the 220kV transmission line survey is finished, and all early works pricing has been validated against the 2022 FEED, positioning the project for a rapid construction ramp-up once full funding and a Final Investment Decision are secured.