Singida Gold Mine to Start Production in March 2023

Singida Gold Project Update

East Africa-focused gold producer, developer and explorer Shanta Gold (AIM: SHG) released an update on the construction progress at the Singida Gold Project in central Tanzania, highlighting that the overall construction activity at the project is 93% complete.

Eric Zurrin, Chief Executive Officer, commented: “We are delighted with the great progress being made at Singida, with construction on schedule for first production next month. The completion of this mine will transform Shanta Gold into a 100,000 oz/pa producer with a diversified resource base, de-risking the balance sheet and providing the business with further financial flexibility.”

For his part, Tanzania’s Minister of Minerals Dr. Doto Biteko congratulated the Company for completing the construction of the mine and said that his ministry has a great responsibility to protect and encourage the presence of investors in the country.

TANZANIA BUSINESS & INVESTMENT GUIDE 2026

For this, he promised to continue to create a better environment for investors with the aim of increasing the productivity of mineral production in the country and promoting the National GDP with mining operations.

Earlier, the Executive Director of Shanta Mining Honest Mrema said that the Shanta-Singida mine will employ more than 220 direct workers and 150 short-term workers.

He also stressed that the company has invested more than 42 million US dollars in the mine whose life is expected to reach 2028.

Mrema also said that Shanta has distributed clean water in the villages surrounding the mine as one of the ways to contribute to the local communities.

Tanzania Gold

Tanzania’s gold reserves are estimated at about 45 million ounces and Tanzania’s gold production in Tanzania stands at around 50t per year.

Shanta Gold’s other mine in Tanzania, the New Luika Gold Mine, is currently the 4th largest mine in the country with gold production of 65,209 ounces in 2022, up 18% from 2021.

Want to know more about Mining in Tanzania? Our free Tanzania Business and Investment Guide 2026 covers Mining, plus regulations, key sectors, and investment opportunities — all in one place.

Download Free Guide
Related Posts
Tanzania Mahenge Graphite Project Map
Read More

Tanzania Mahenge Graphite Project Early Works to Complete by Mid-2026 Ahead of Final Investment Decision

Black Rock Mining's early works program at the Mahenge Graphite Project in Tanzania's Ulanga region is nearing completion, with final earthworks and resettlement activities expected to wrap up by late Q2 2026. Community compensation for the lower access road has been completed, the 220kV transmission line survey is finished, and all early works pricing has been validated against the 2022 FEED, positioning the project for a rapid construction ramp-up once full funding and a Final Investment Decision are secured.
Tanzania Panda Hill Niobium Agreement Signing
Read More

Tanzania Signs Niobium Project Agreement Targeting 4% of Global Output

The Government of Tanzania and Panda Hill Tanzania Limited have officially signed an agreement to advance the Panda Hill niobium project in Mbeya. The deal formalizes government participation through a 16% free carried interest, positions Tanzania to contribute 4% of global niobium supply, and includes the construction of a ferroniobium plant, local value addition, and thousands of jobs over the project’s life.