East Africa Crude Oil Pipeline Construction Reaches 66.5% Completion

The East Africa Crude Oil Pipeline project reached 66.5% completion as of Q2 2025, according to the latest company newsletter. Progress includes 762 km welded, over 325 km coated, and over 104 km lowered, alongside major works at pump stations, storage tanks, and the jetty in Tanga.
EACOP Q2 2025 Update

The East African Crude Oil Pipeline (EACOP) project has reached 66.5% completion, according to the latest newsletter released by the company.

To date, 762 km of pipeline have been welded, more than 325 km coated, and over 104 km lowered into the ground.

The newsletter details the construction progress across all project components as of Q2 2025.

Tanzania Investment Guide 2026 Free Edition

Pipeline construction is ongoing across three lots: Lot 1 from Lake Albert in Uganda to the Mutukula border, Lot 2 from the border to Igugono in Singida, and Lot 3 from Igugono to Chongoleani in Tanga.

Since welding commenced in September 2024, 500 km of pipe have been welded, 200 km coated with Liquid Epoxy, and 54 km lowered into trenches.

Horizontal Directional Drilling works are advancing at the Sigi River, with casing and pipeline welding completed and reaming works progressing.

Main Camps and Pipe Yards are operational, with 11 camps accommodating 2,325 people. Activities include pipe delivery to the right-of-way, electrical installations, and environmental management such as food composting.

Progress has also been recorded at pump stations, where 30,220 cubic meters of priority concrete and 8,583 linear meters of underground piping have been completed.

Tanzania Investment Guide 2026 Full Edition

Pump Station 4 leads with 60% progress, followed by Pump Station 6 at 55% and Pump Station 3 at 47%. Work continues at other stations, with piping, steel structures, and installations underway.

At the Thermal Insulation Plant, inaugurated in March 2024, 787 km of pipes have been coated with polyurethane foam and 718 km dispatched for welding and stringing. Repairs of coating damage during transport are ongoing.

The marine terminal in Tanga has reached 33% completion, with seven out of eight site-fabricated storage tanks erected and storage tank works at 80% progress.

Tank A is undergoing hydrotesting, while other tanks are at different stages of welding and assembly.

Jetty construction is advancing, with 166 piles driven and 100 crossheads installed in shallow and deep water.

Prefabricated trestle modules have been installed, and work has commenced on the abutment in Chongoleani, Tanga.

The newsletter concludes that the groundwork for the delivery of First Oil is steadily taking shape, with pipeline welding, coating, and supporting infrastructure such as pump stations, terminals, and jetty works moving forward.

Want to know more about Energy in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Energy, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Related Posts
Tanzania Julius Nyerere Hydropower Project (JNHPP)
Read More

Tanzania Electricity Surplus Hits 2,375 MW As Julius Nyerere Hydropower Project Is Officially Launched

The Julius Nyerere Hydropower Project's 2,115MW plant lifted Tanzania's installed generation capacity to 4,646MW against peak demand of 2,271MW, with a surplus of 2,375MW, after President Samia Suluhu Hassan's inauguration on 22 August 2026. The government has signed an agreement to export power to Zambia and reached a trading arrangement with Kenya, while a newly completed 400kV Chalinze-Dodoma transmission line lifted national peak demand by 150MW within three days of coming online.
Presidents Samia Suluhu Hassan and Yoweri Museveni witness the Tanga Regional Energy Hub MoU signing, State House Dar es Salaam
Read More

Tanzania, Uganda Sign MoU for USD 20 Billion Tanga Energy Hub

Tanzania and Uganda signed a Memorandum of Understanding at State House on 6 August 2026 to develop Tanga as a Regional Energy Hub, a deal Tanzania's Energy Minister said could attract investment exceeding USD 20 billion. The agreement, signed by the Uganda National Oil Company, the Tanzania Petroleum Development Corporation, and Vitol Bahrain E.C., covers petroleum storage, refining, logistics, and distribution infrastructure at the port of Tanga, building on the East African Crude Oil Pipeline.
Samia Suluhu Hassan Africa50 Forum Dar es Salaam 2026
Read More

Tanzania President Calls for Faster Infrastructure Delivery Via PPPs as Country Signs Five Agreements on Power Transmission, Gas and Health

Tanzania President Samia Suluhu Hassan called for faster infrastructure delivery through public-private partnerships (PPPs) as Tanzania signed five agreements at Africa50's Infra for Africa Forum, covering an electricity transmission PPP with TANESCO, natural gas supply to local industry with TPDC and TAQA Arabia, and expanded kidney dialysis care. Africa50 secured USD 70 million in new capital from British International Investment, the Italian Climate Fund and Proparco, the private sector financing arm of the French Development Agency group (AFD).
Tanzania Contract 100 MW Kishapu Solar Project Phase Two
Read More

Tanzania Signs TZS 204.4 Billion Contract for 100 MW Kishapu Solar Project Phase Two

Tanzania has signed a contract worth approximately TZS 204.4 billion with Sagemcom Energy & Telecom SAS and STEG International Services for the 100 MW second phase of the Kishapu Solar Power Project in Ngunga, Shinyanga Region, taking the full 150 MW project's cost to approximately TZS 323 billion. The contract follows completion of the project's 50 MW first phase, which cost TZS 118.6 billion and became Tanzania's first grid-connected utility-scale solar plant in March 2026.