East African Crude Oil Pipeline Reaches 82% Completion

The East African Crude Oil Pipeline (EACOP) has reached 82% overall completion as of April 2026, with construction progressing across pipeline sections, pump stations, and the Chongoleani Marine Terminal in Tanga. The 1,443-kilometre pipeline is advancing steadily toward First Oil, with all line pipes delivered and the marine jetty at 88.1% completion.
EACOP April 2026 Update

The East African Crude Oil Pipeline (EACOP) project has reached 82% overall completion, according to the company’s latest project update for April 2026, marking steady progress across all major construction fronts as the project advances toward First Oil.

Construction activities have advanced across key sections of the pipeline, pump stations, and terminal infrastructure during the first quarter of 2026.

Significant milestones have been achieved in welding, trenching, pump station development, and marine storage terminal works.

Tanzania Investment Guide 2026 Free Edition

The marine jetty has reached 88.1% completion, with precast elements installation and Marine Loading Arms (MLA) A, B, and C mechanical, hydraulic, and electrical installation works now complete.

Preparations are currently underway to relocate the MLAs from the quay wall to the storage barge.

On 10 January 2026, the project reached a key milestone in Uganda with the arrival of the final pipe truck at Main Camp and Pipe Yard 4 (MCPY4), completing the supply of all line pipes required for the pipeline and signalling the end of a major procurement and logistics phase.

In February 2026, Tanzania’s Prime Minister, Hon. Dkt. Mwigulu Nchemba, visited the Marine Tanks Terminal and Jetty in Chongoleani, Tanga, to assess firsthand the progress achieved to date.

The visit was part of the Government’s ongoing efforts to monitor the advancement of strategic national projects.

Tanzania Investment Guide 2026 Full Edition

The Prime Minister commended the progress achieved during his visit, reaffirmed the Government’s commitment to supporting the successful delivery of the project, and emphasised that EACOP represents a strategic investment that will strengthen regional energy cooperation, stimulate economic growth, and create long-term opportunities for Tanzanians.

Guillaume Delout, Managing Director of EACOP, stated: “As we progress further into 2026, our focus remains firmly aligned toward safe, timely, and efficient project completion as we advance toward First Oil.”

East African Crude Oil Pipeline

EACOP is a 1,443-kilometre heated crude oil pipeline being developed to transport oil from the Tilenga and Kingfisher oil fields in Uganda to the Chongoleani Marine Terminal near Tanga on Tanzania’s coast.

The pipeline is a joint venture between TotalEnergies, the Uganda National Oil Company (UNOC), the Tanzania Petroleum Development Corporation (TPDC), and CNOOC, and represents one of the largest infrastructure investments in East Africa.

Upon completion, EACOP is expected to have a capacity of up to 246,000 barrels per day, with Tanzania set to benefit from transit fees, local employment, and related infrastructure development along the pipeline corridor.

Want to know more about Energy in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Energy, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources.

Download Free OverviewGet the Full Guide
Related Posts
Tanzania ASSESSMENT OF ECONOMIC IMPACTS ON TANZANIA ARISING FROM THE GULF CRISIS
Read More

Tanzania Gulf Crisis Report Rates Energy, Food, Transport, Tourism and Budget at High Risk

A May 2026 rapid assessment by Tanzania's National Planning Commission and UNDP rates energy, food, transport, tourism and the Government budget at high risk from the Gulf crisis, which raised Dar es Salaam fuel prices by up to 69% between January and May 2026. The report flags a possible TZS 153.7 billion monthly customs revenue shortfall and fuel subsidy needs rising to TZS 1,384.2 billion by July, alongside buffers including a 124% food self-sufficiency ratio, USD 6.3 billion in reserves and 57 trillion cubic feet of gas.
Tanzania-Rwanda energy cooperation agreement 2026 Hassan Kagame
Read More

Tanzania and Rwanda Sign Energy Cooperation Agreement Covering Power Trade, Oil, Gas and LNG

Tanzania and Rwanda signed a bilateral energy cooperation agreement covering cross-border electricity trade, joint power infrastructure development, and petroleum product distribution. The deal also extends to oil and gas exploration, LNG project opportunities, and the use of artificial intelligence in the energy sector, building on the existing 80 MW Rusumo interconnection, which has synchronized the grids of Tanzania, Rwanda, and Burundi since March 2024.
Russia Maxim Reshetnikov Tanzania Kitila Mkumbo
Read More

Tanzania and Russia Agree to Open Industry, Energy, and Infrastructure to Joint Investment

Tanzania and Russia have agreed to deepen investment cooperation in industry, energy, transport infrastructure, and air transport, with value-addition processing, production technology, and goods transportation named as priority areas at the Third Joint Intergovernmental Commission held in Arusha on 15–16 May 2026, which drew 120 Russian companies. The deals also cover Russian investment in mining, agriculture, and ICT, direct Air Tanzania (ATCL) flights to Russia, and a signed agreement to promote the Swahili language in Russia.