USD 942M Kabanga Nickel Project Moves Closer to Implementation, FID Expected in 2026

The Kabanga Nickel Project has moved closer to implementation after Lifezone Metals (NYSE: LZM) Executive Chairman Keith Liddell and Treasury Registrar Nehemiah Mchechu briefed President Samia Suluhu Hassan on 8 June 2026, with both sides confirming an agreed project structure and turning to finalise the refinery and beneficiation component. The USD 942 million project is targeting a final investment decision in 2026 and is expected to generate USD 2.4 billion in corporate income taxes and around 1,090 jobs.
Kabanga Nickel Deposit

Tanzania’s Kabanga Nickel Project, a mining and industrial investment valued at around USD 942 million, has moved closer to implementation after the Government and Lifezone Metals (NYSE: LZM) agreed on a project structure and turned their focus to finalising the refinery and beneficiation component.

The progress was announced by the Directorate of Presidential Communications, State House, on 9 June 2026, a day after a high-level briefing to President Samia Suluhu Hassan delivered by Keith Liddell, Founder and Executive Chairman of Kabanga Nickel Limited and Lifezone Metals (NYSE: LZM), together with Treasury Registrar Nehemiah Mchechu.

Both sides confirmed substantial progress, a common understanding on project structure, and an agreement on how beneficiation will be carried out inside Tanzania.

Tanzania Investment Guide 2026 Free Edition

Preparations on the mining side are largely advanced. Efforts are now focused on finalising arrangements for the refinery and beneficiation component.

The project is expected to deliver benefits through local content participation, taxes, dividends, technology transfer and industrial development.

“It was an absolute honour to meet Her Excellency. She reaffirmed her commitment to the project and her support for advancing it under the agreed implementation plan,” Mr. Liddell said.

“The mine is coming. The beneficiation is coming. Be assured that we are working closely with Team Tanzania to deliver this project as quickly as possible,” he added.

“We have developed a structure that both the Government and investors are comfortable with. We are now working to finalise the remaining elements so that implementation can begin,” Mr. Mchechu said.

Tanzania Investment Guide 2026 Full Edition

“These efforts are fully aligned with the vision of Her Excellency President Samia Suluhu Hassan, who is keen to see this project move from negotiations to implementation,” he added.

“This is a game-changing project. Together with other strategic investments, it has the potential to accelerate Tanzania’s industrial transformation and long-term development goals,” he said.

About the Kabanga Nickel Project

The Kabanga Nickel Project is located in Ngara district, Kagera Region, in northwestern Tanzania, and is regarded as one of the world’s largest and highest-grade undeveloped nickel sulphide deposits.

It is held by Tembo Nickel Corporation Limited, in which Lifezone Metals (NYSE: LZM) owns 84% through Kabanga Nickel Limited, while the Government of Tanzania holds a non-dilutable 16% free-carried interest.

Lifezone took full ownership of Kabanga Nickel Limited in July 2025 after acquiring BHP’s 17% stake, and also controls 100% of the project’s offtake.

A feasibility study released in July 2025 reported proven and probable reserves of 52.2 million tonnes grading 1.98% nickel, 0.27% copper and 0.15% cobalt, supporting an 18-year mine life at an annual throughput of 3.4 million tonnes.

The study put the project’s after-tax net present value at about USD 1.6 billion, with an internal rate of return of 23.3% and capital costs of around USD 942 million, placing Kabanga in the first quartile of the global nickel cost curve.

Over its life, the mine is expected to produce 902,000 tonnes of nickel, 134,000 tonnes of copper and 69,000 tonnes of cobalt in intermediate form, generating an estimated USD 1.2 billion in royalties, fees, levies and duties and USD 2.4 billion in corporate income taxes for Tanzania, alongside about 1,090 direct jobs, most of them held by Tanzanians.

Beneficiation is planned at the Kahama multi-metal processing refinery in the Buzwagi Special Economic Zone in Shinyanga, using Lifezone’s Hydromet technology, which the company says offers lower energy use and emissions than conventional smelting.

Lifezone Metals (NYSE: LZM) is targeting a final investment decision in 2026, having raised USD 75 million in the second half of 2025 and secured a USD 60 million bridge facility, with the US International Development Finance Corporation having completed environmental and social due diligence on the project.

Related Posts
Tanzania Mineral Testing Laboratory Dodoma 3d plan
Read More

Dodoma Mineral Testing Laboratory on Track for September 2027 Completion

The Geological Survey of Tanzania (GST) says construction of its Dodoma mineral testing laboratory in Kizota, Dodoma, is progressing on schedule, with completion set for September 2027, a year after Minister for Minerals Anthony Mavunde laid the foundation stone in August 2025. The TZS 14.3 billion (approx. USD 5.4 million) facility is expected to become the largest of its kind in East and Central Africa, offering internationally accredited testing services and easing long-standing sample-analysis delays for artisanal and small-scale miners.
IMF Tanzania flag
Read More

IMF Approves USD 443.9 Million for Tanzania, Projects 6.2% GDP Growth Supported by Mining, Agriculture, and Tourism

The IMF Executive Board has approved an immediate disbursement of USD 443.9 million to Tanzania after completing the final reviews under the Extended Credit Facility and Resilience and Sustainability Facility programmes. The IMF said Tanzania maintained strong economic growth and macroeconomic stability while highlighting the need for continued reforms and fiscal consolidation.
Tanzania Grinding-Ball
Read More

Chinese Company to Build Grinding-Ball Factory at Buzwagi SEZ

China's Oriental Casting and Forging Ltd plans to establish a factory for steel grinding balls and other mining consumables at the Buzwagi Special Economic Zone in Kahama, Shinyanga, following a meeting between Minister of Minerals Anthony Mavunde and the company's managing director Hou Songcun. The project is part of Tanzania's push to manufacture mining consumables locally, cut import dependence and position itself as a regional supply hub, though no investment value or job figures have been disclosed.
Tanzania Mining Revenues 2025-2026
Read More

Tanzania Mining Revenue Hits TZS 1.39 Trillion in 2025/26, Beating Target by 16%

Tanzania mining revenue reached TZS 1.394 trillion (± USD 558 million) in the 2025/26 financial year, surpassing the annual target of TZS 1.2 trillion by 16.13% and marking a 30.2% increase over the TZS 1.071 trillion collected in 2024/25. The result caps a period of rapid growth for the sector, whose GDP contribution averaged 11.9% in 2025 and whose mineral exports rose 31.1% to USD 5.4 billion.