Epanko Graphite Project Updated Feasibility Study Confirms USD 516 Million Value And 73,000 Tonnes Annual Output

EcoGraf has released an updated Bankable Feasibility Study for the Epanko Graphite Project in Tanzania, confirming a 73,000 tonnes per annum operation and a NPV of USD 516 million before tax. The study supports project financing, expansion to 390,000 tonnes per annum, and long-term battery market demand growth.
Tanzania Epanko Graphite Project Map

EcoGraf (ASX: EGR; FSE: FMK) has released an updated Bankable Feasibility Study for the Epanko Graphite Project in Tanzania, confirming a 73,000 tonnes per annum operation over the first 15 years and a pre-tax net present value (NPV) of USD 516 million, supporting the next phase of project financing.

The updated study is based on an Ore Reserve of 16.7 million tonnes at 8.2% total graphite carbon, including 7.1 million tonnes in Proven and 9.6 million tonnes in Probable categories, and reflects a 21.7% increase in planned plant throughput to 73,000 tonnes per annum.

The study outlines an internal rate of return of 31.1% and projected annual EBITDA of USD 85.7 million, calculated using a life-of-mine basket price of USD 1,746 per tonne in real 2025 terms, while total capital expenditure includes USD 181.2 million for construction and establishment and USD 18.1 million for the Resettlement Action Plan, including contingencies.

Tanzania Investment Guide 2026 Free Edition

An Independent Engineers Review conducted in parallel with the study confirmed that technical components have been advanced to meet international project financing standards and the Global Industry Standard on Tailings Management, while Environmental and Social Management Planning has been completed in line with Tanzanian legislation, IFC Performance Standards and World Bank Group Environmental Health and Safety Guidelines.

The company stated that its debt financing program is at an advanced stage under the leadership of KfW IPEX-Bank, and that binding offtake and in-principle sales agreements are in place covering 40,000 tonnes per annum of production with existing partners and Germany-based ThyssenKrupp Metallurgical Products GmbH.

A further 20,000 tonnes per annum is expected to convert into binding offtake agreements once production commences, while planning is underway for a Stage 2 expansion to 130,000 tonnes per annum and longer-term expansion studies outline the potential to increase production to 390,000 tonnes per annum within 10 years.

The project is fully covered under a single Special Mining Licence and benefits from grid power and proximity to an established transport corridor supported and funded by the European Commission, positioning Epanko to supply graphite to battery and electric vehicle markets outside China.

EcoGraf Managing Director Andrew Spinks commented: “The combination of the market-leading quality of the Epanko Resource, with the completion of one of the most rigorous technical due diligence programs, cements Epanko as a world-class graphite project, poised for development.”

Tanzania Investment Guide 2026 Full Edition

He added: “The Company is now positioned well to take advantage of the forecasted huge growth in graphite demand, on the back of the increased electric vehicle and energy storage battery boom. The planned Tanzanian midstream and end-user located downstream processing plants are expected to provide the company with significant growth and substantial cash flow generation.”

Graphite demand is forecast to exceed projected global supply from 2026, driven by increased use of natural graphite in lithium-ion batteries for electric mobility and energy storage systems, while recent export restrictions by China on certain dual-use goods, including graphite shipments to Japan, have highlighted supply chain risks for battery manufacturers.

Tanzania hosts several graphite projects targeting international battery markets, with Epanko positioned as a large-scale development aimed at supplying ex-China markets and supporting downstream processing expansion in North America, Europe, and Asia.

Want to know more about Mining in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Mining, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources.

Download Free OverviewGet the Full Guide
Related Posts
Tanzania Mineral Testing Laboratory Dodoma 3d plan
Read More

Dodoma Mineral Testing Laboratory on Track for September 2027 Completion

The Geological Survey of Tanzania (GST) says construction of its Dodoma mineral testing laboratory in Kizota, Dodoma, is progressing on schedule, with completion set for September 2027, a year after Minister for Minerals Anthony Mavunde laid the foundation stone in August 2025. The TZS 14.3 billion (approx. USD 5.4 million) facility is expected to become the largest of its kind in East and Central Africa, offering internationally accredited testing services and easing long-standing sample-analysis delays for artisanal and small-scale miners.
IMF Tanzania flag
Read More

IMF Approves USD 443.9 Million for Tanzania, Projects 6.2% GDP Growth Supported by Mining, Agriculture, and Tourism

The IMF Executive Board has approved an immediate disbursement of USD 443.9 million to Tanzania after completing the final reviews under the Extended Credit Facility and Resilience and Sustainability Facility programmes. The IMF said Tanzania maintained strong economic growth and macroeconomic stability while highlighting the need for continued reforms and fiscal consolidation.
Tanzania Grinding-Ball
Read More

Chinese Company to Build Grinding-Ball Factory at Buzwagi SEZ

China's Oriental Casting and Forging Ltd plans to establish a factory for steel grinding balls and other mining consumables at the Buzwagi Special Economic Zone in Kahama, Shinyanga, following a meeting between Minister of Minerals Anthony Mavunde and the company's managing director Hou Songcun. The project is part of Tanzania's push to manufacture mining consumables locally, cut import dependence and position itself as a regional supply hub, though no investment value or job figures have been disclosed.
Tanzania Mining Revenues 2025-2026
Read More

Tanzania Mining Revenue Hits TZS 1.39 Trillion in 2025/26, Beating Target by 16%

Tanzania mining revenue reached TZS 1.394 trillion (± USD 558 million) in the 2025/26 financial year, surpassing the annual target of TZS 1.2 trillion by 16.13% and marking a 30.2% increase over the TZS 1.071 trillion collected in 2024/25. The result caps a period of rapid growth for the sector, whose GDP contribution averaged 11.9% in 2025 and whose mineral exports rose 31.1% to USD 5.4 billion.