Epanko Graphite Project Updated Feasibility Study Confirms USD 516 Million Value And 73,000 Tonnes Annual Output

EcoGraf has released an updated Bankable Feasibility Study for the Epanko Graphite Project in Tanzania, confirming a 73,000 tonnes per annum operation and a NPV of USD 516 million before tax. The study supports project financing, expansion to 390,000 tonnes per annum, and long-term battery market demand growth.
Tanzania Epanko Graphite Project Map

EcoGraf (ASX: EGR; FSE: FMK) has released an updated Bankable Feasibility Study for the Epanko Graphite Project in Tanzania, confirming a 73,000 tonnes per annum operation over the first 15 years and a pre-tax net present value (NPV) of USD 516 million, supporting the next phase of project financing.

The updated study is based on an Ore Reserve of 16.7 million tonnes at 8.2% total graphite carbon, including 7.1 million tonnes in Proven and 9.6 million tonnes in Probable categories, and reflects a 21.7% increase in planned plant throughput to 73,000 tonnes per annum.

The study outlines an internal rate of return of 31.1% and projected annual EBITDA of USD 85.7 million, calculated using a life-of-mine basket price of USD 1,746 per tonne in real 2025 terms, while total capital expenditure includes USD 181.2 million for construction and establishment and USD 18.1 million for the Resettlement Action Plan, including contingencies.

Tanzania Investment Guide 2026 Free Edition

An Independent Engineers Review conducted in parallel with the study confirmed that technical components have been advanced to meet international project financing standards and the Global Industry Standard on Tailings Management, while Environmental and Social Management Planning has been completed in line with Tanzanian legislation, IFC Performance Standards and World Bank Group Environmental Health and Safety Guidelines.

The company stated that its debt financing program is at an advanced stage under the leadership of KfW IPEX-Bank, and that binding offtake and in-principle sales agreements are in place covering 40,000 tonnes per annum of production with existing partners and Germany-based ThyssenKrupp Metallurgical Products GmbH.

A further 20,000 tonnes per annum is expected to convert into binding offtake agreements once production commences, while planning is underway for a Stage 2 expansion to 130,000 tonnes per annum and longer-term expansion studies outline the potential to increase production to 390,000 tonnes per annum within 10 years.

The project is fully covered under a single Special Mining Licence and benefits from grid power and proximity to an established transport corridor supported and funded by the European Commission, positioning Epanko to supply graphite to battery and electric vehicle markets outside China.

EcoGraf Managing Director Andrew Spinks commented: “The combination of the market-leading quality of the Epanko Resource, with the completion of one of the most rigorous technical due diligence programs, cements Epanko as a world-class graphite project, poised for development.”

TanzaniaInvest Capital Markets Report Banner

He added: “The Company is now positioned well to take advantage of the forecasted huge growth in graphite demand, on the back of the increased electric vehicle and energy storage battery boom. The planned Tanzanian midstream and end-user located downstream processing plants are expected to provide the company with significant growth and substantial cash flow generation.”

Graphite demand is forecast to exceed projected global supply from 2026, driven by increased use of natural graphite in lithium-ion batteries for electric mobility and energy storage systems, while recent export restrictions by China on certain dual-use goods, including graphite shipments to Japan, have highlighted supply chain risks for battery manufacturers.

Tanzania hosts several graphite projects targeting international battery markets, with Epanko positioned as a large-scale development aimed at supplying ex-China markets and supporting downstream processing expansion in North America, Europe, and Asia.

Want to know more about Mining in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Mining, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Related Posts
Tanzania Epanko Graphite Project Map
Read More

Tanzania’s Epanko Graphite Project Could Boost Output by 20%

EcoGraf's Epanko Graphite Project in Tanzania could lift Stage 1 output 20% to 87,600 tonnes a year and cut operating costs up to 6.8%, per a Value Engineering Review. The 73,000 tonnes per annum Updated Bankable Feasibility Study remains the basis for project financing.
Tanzania Fitch Ratings
Read More

Fitch Revises Tanzania Outlook to Positive, Affirms ‘B+’ Rating, Forecasts GDP Growth of 5.8% in 2026 Driven by Tourism and Mining

Fitch Ratings revised Tanzania's outlook to positive from stable while affirming the sovereign rating at 'B+', citing strengthening reserves and a gradual decline in government debt, warning, however, that the credit rating remains constrained by weak governance and low government revenue. The agency forecasts real GDP growth of 5.8% in 2026 and an average of 6.1% in 2027 and 2028, driven by public investment, tourism, the country's role as a regional logistics hub, and expansion in the mining sector.
Tanzania Samia Suluhu Hassan DRC Felix Tshisekedi
Read More

DRC to Build Dry Port in Dar es Salaam, Deepen Transport and Mining Ties with Tanzania

The Democratic Republic of the Congo (DRC) has begun preparations to build a dry port in Dar es Salaam that will provide customs, cargo handling, mineral certification, and quality control services for Congolese goods moving through Tanzania, President Félix Tshisekedi announced during a state visit to Tanzania on 18 August 2026. The DRC is among the largest users of Tanzanian ports, with approximately 7.2 million tonnes of cargo handled in 2023, as the two countries agreed to accelerate transport, trade, and mining cooperation along the Central Corridor.