East Africa Crude Oil Pipeline Construction Reaches 72% Completion

The East Africa Crude Oil Pipeline project reached 72% completion as of Q3 2025, according to the latest company newsletter. Progress includes 800 km welded, over 300 km coated, and over 115 km lowered into the ground, alongside major works at pump stations, storage tanks, and the jetty in Tanga.
EACOP Q2 2025 Update

The East African Crude Oil Pipeline (EACOP) project has reached 72% completion, according to the latest newsletter released by the company covering Q3 of 2025.

Pipeline Progress Summary

Pipeline construction activities are progressing across all 3 lots during Quarter 3.

Tanzania Investment Guide 2026 Free Edition

Lot 1: Lake Albert, Bullisa District, Uganda to Mutukula Boarder, Kyotera District, Uganda.

Lot 2: Mutukula Boarder, Kyotera District Uganda, to Igugono, Singida Region, Tanzania.

Lot 3: Igugono, Singida Region Tanzania, to Chongoleani, Tanga Region Tanzania.

To date, 800 km of pipeline has been welded, 300 km coated with Liquid Epoxy, and 115 km lowered into the ground. Works commenced for the installation of High high-voltage cables along the pipeline route.

Horizontal Directional Drilling (HDD) at the Sigi River is ongoing, 38-inch, 44-inch and 50-inch reaming works were completed during the quarter, and works commenced for the 54-inch reaming in preparation for the pipe to be pulled through.

Tanzania Investment Guide 2026 Full Edition

Marine Terminal & Tanks Progress Summary

Marine Terminal progress is at 38.5%. Works commenced for the erection of steel structures of the Power Generator Building. Nitrogen and Deluge Skids were installed on foundations.

Storage Tanks progress is at 83%. Tank A completed hydrotesting and was ready for dewatering into Tank B.

Tank B completed roof drainage system welding, and the pre-Hydrotest punch list was cleared. Preparation is ongoing for the hydrotest to commence.

Tank C floating roof plates and attachments welding is ongoing. Tank D is finalising the erection and welding of floating roof attachments, piping erection, and welding works commenced.

Jetty Progress Summary

The Jetty is the pipeline marine export terminal infrastructure at the Tanga Port in Tanzania, which will serve as the offshore loading facility where crude oil transported through EACOP will be loaded into crude oil export tankers.

The construction of the Jetty achieved significant milestones in Quarter 3 with the launching girder completing piling activities in the shallow area and the completion of trestle installations in the deep area.

180 piles and 110 crossheads had been installed in the deeper and shallower water. Pre-fabricated modules to form the trestle are also being installed in the deep and shallow water. At the end of the quarter, 97 modules had been installed.

At the Abutment in Chongoleani, concrete casting was completed for Bents 95 to 99. Rock placing is ongoing.

Commenting on the progress, John Bosco Habumugisha, General Manager Uganda for EACOP, wrote in his message: “The period from July to September has been marked by steady advancement across our operations. In this past quarter, we have deepened our collaboration with local communities, reinforced our environmental and safety commitments, and remained focused on ensuring that every step forward brings long-term benefits to the people of Uganda and Tanzania and the East African Region.”

Want to know more about Energy in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Energy, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Related Posts
Presidents Samia Suluhu Hassan and Yoweri Museveni witness the Tanga Regional Energy Hub MoU signing, State House Dar es Salaam
Read More

Tanzania, Uganda Sign MoU for USD 20 Billion Tanga Energy Hub

Tanzania and Uganda signed a Memorandum of Understanding at State House on 6 August 2026 to develop Tanga as a Regional Energy Hub, a deal Tanzania's Energy Minister said could attract investment exceeding USD 20 billion. The agreement, signed by the Uganda National Oil Company, the Tanzania Petroleum Development Corporation, and Vitol Bahrain E.C., covers petroleum storage, refining, logistics, and distribution infrastructure at the port of Tanga, building on the East African Crude Oil Pipeline.
Samia Suluhu Hassan Africa50 Forum Dar es Salaam 2026
Read More

Tanzania President Calls for Faster Infrastructure Delivery Via PPPs as Country Signs Five Agreements on Power Transmission, Gas and Health

Tanzania President Samia Suluhu Hassan called for faster infrastructure delivery through public-private partnerships (PPPs) as Tanzania signed five agreements at Africa50's Infra for Africa Forum, covering an electricity transmission PPP with TANESCO, natural gas supply to local industry with TPDC and TAQA Arabia, and expanded kidney dialysis care. Africa50 secured USD 70 million in new capital from British International Investment, the Italian Climate Fund and Proparco, the private sector financing arm of the French Development Agency group (AFD).
Tanzania Contract 100 MW Kishapu Solar Project Phase Two
Read More

Tanzania Signs TZS 204.4 Billion Contract for 100 MW Kishapu Solar Project Phase Two

Tanzania has signed a contract worth approximately TZS 204.4 billion with Sagemcom Energy & Telecom SAS and STEG International Services for the 100 MW second phase of the Kishapu Solar Power Project in Ngunga, Shinyanga Region, taking the full 150 MW project's cost to approximately TZS 323 billion. The contract follows completion of the project's 50 MW first phase, which cost TZS 118.6 billion and became Tanzania's first grid-connected utility-scale solar plant in March 2026.
Eastern Africa Power Pool (EAPP) 2026 Council of Ministers Meeting
Read More

Eastern Africa Power Pool Ministers Agree to Accelerate Regional Electricity Market

Eastern Africa Power Pool (EAPP) member states have agreed to speed up the implementation of a regional electricity market aimed at expanding cross-border electricity trade and strengthening energy security. Tanzania said the initiative will support industrial growth, attract investment, and improve the reliability of electricity supply across the region.