Singida Gold Project Construction on Track for Production in 2023

SINGIDA GOLD PROJECT CONSTRUCTION

East Africa-focused gold producer, developer, and explorer Shanta Gold (AIM: SHG) has recently provided an update on the construction progress at the Singida Gold Project in Central Tanzania, confirming it remains on track for the first gold production to take place in early 2023.

Construction of the Singida gold project commenced in October 2020.

Shanta Gold CEO Eric Zurrin commented: “The encouraging results of our grade control drilling at Singida reinforces our confidence in the strength of the production profile, especially for the first 18-24 months of production.”

Tanzania Investment Guide 2026 Free Edition

The Singida Gold Proejct

The Singida project is an open-pit gold project covering an area of about 98 km2 located in the greenstone belt within the Ikungi district in the Singida Region of central Tanzania.

Total capital investment in the project comes at USD 26 million over a 24-month construction period. The investment is funded by Shanta’s internal cash flows.

Expected annual production is projected at 32,000 ounces over an initial life of mine of seven years.

Tanzania Gold

Tanzania’s gold reserves are estimated at about 45 million ounces.

Tanzania’s gold production increased by more than 700% over the past 25 years, from 5 to 40-50 tonnes per year, while South Africa’s production of gold decreased from over 500 tonnes in 1990 to 117 tonnes in 2018.

Tanzania Investment Guide 2026 Full Edition

Current active gold mines include Buckreef, Bulyanhulu, Buzwagi, North Mara, Geita, Golden Pride, and New Luika (Shanta Gold).

Want to know more about Mining in Tanzania? Our free overview of the Tanzania Business and Investment Guide 2026 covers Mining, plus key sectors and investment opportunities. The complete 141-page edition includes policies, taxation, key regulations, full macroeconomic data, and sources, and is also available at no cost upon completion of a short form.

Download Free OverviewGet the Full Edition for Free
Related Posts
Tanzania gold production 2025-2026
Read More

Tanzania Gold Production Reaches 67.8 Tonnes, Central Bank Buys 75.64%

Tanzania's Ministry of Minerals reported that the country produced 67.8 tonnes of gold worth TZS 18.4 trillion in the 2025/26 financial year, with 28,701 kilograms sold through five domestic refineries. The Bank of Tanzania purchased 21,710 kilograms, equivalent to 75.64% of that volume, under its Domestic Gold Purchase Programme to strengthen the country's foreign reserves.
North Rukwa Project helium licence map, Tanzania
Read More

Noble Helium Raises AUD 12 Million, Secures Rig for North Rukwa Drilling

Noble Helium Limited (ASX:NHE) raised AUD 12 million and converted AUD 6.603 million of debt to equity during the June 2026 quarter, ending with AUD 6.689 million in cash, according to its latest quarterly report. The company has contracted a rig to drill two wells at its Kinambo prospect within the North Rukwa Project in Tanzania, with mobilisation expected in August 2026.
Tanzania Mineral Testing Laboratory Dodoma 3d plan
Read More

Dodoma Mineral Testing Laboratory on Track for September 2027 Completion

The Geological Survey of Tanzania (GST) says construction of its Dodoma mineral testing laboratory in Kizota, Dodoma, is progressing on schedule, with completion set for September 2027, a year after Minister for Minerals Anthony Mavunde laid the foundation stone in August 2025. The TZS 14.3 billion (approx. USD 5.4 million) facility is expected to become the largest of its kind in East and Central Africa, offering internationally accredited testing services and easing long-standing sample-analysis delays for artisanal and small-scale miners.